IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

188

matching recommendations
Reset
SIC 20 Food and Kindred Products
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
OR0777 # 01 Y:2023 01 2023 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $8,479 $0 Implemented
OR0777 # 02 Y:2023 02 2023 INSTALL COMMON HEADER ON COMPRESSORS $2,832 $6,989 Implemented
OR0777 # 03 Y:2023 03 2023 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $2,570 $0 Implemented
UW2209 # 02 Y:2022 02 2022 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,845 $6,616 Implemented
UW2209 # 04 Y:2022 04 2022 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS $2,276 $0 Implemented
UW2209 # 01 Y:2022 01 2022 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $5,907 $2,080 Implemented
UW2207 # 01 Y:2022 01 2022 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $2,161 $0 Implemented
UW2207 # 02 Y:2022 02 2022 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $685 $112 Implemented
UW2207 # 04 Y:2022 04 2022 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $3,631 $2,080 Implemented
UW2205 # 01 Y:2022 01 2022 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $4,244 $12,938 Implemented
UW2205 # 03 Y:2022 03 2022 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $3,984 $15,999 Implemented
OR0712 # 06 Y:2018 06 2018 USE SMALL NUMBER OF HIGH OUTPUT UNITS INSTEAD OF MANY SMALL INEFFICIENT UNITS $6,403 $30,000 Implemented
OR0712 # 05 Y:2018 05 2018 INSULATE BARE EQUIPMENT $17,619 $17,511 Implemented
OR0712 # 01 Y:2018 01 2018 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS $200,991 $689,600 Implemented
BS0079 # 02 Y:2016 02 2016 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME $154 $148 Implemented
OR0661 # 01 Y:2015 01 2015 REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT $52,251 $18,807 Implemented
OR0661 # 03 Y:2015 03 2015 INSULATE BARE EQUIPMENT $1,989 $170 Implemented
OR0660 # 03 Y:2015 03 2015 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $1,283 $1,500 Implemented
OR0660 # 01 Y:2015 01 2015 CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS $135,000 $250,000 Implemented
OR0660 # 02 Y:2015 02 2015 INSTALL OCCUPANCY SENSORS $3,310 $8,500 Implemented
OR0659 # 04 Y:2015 04 2015 INSULATE BARE EQUIPMENT $6,192 $8,000 Implemented
OR0659 # 02 Y:2015 02 2015 MINIMIZE CONTAMINATION OF WATER BEFORE TREATMENT $26,260 $7,200 Implemented
OR0659 # 07 Y:2015 07 2015 INSULATE BARE EQUIPMENT $1,353 $8,000 Implemented
OR0659 # 01 Y:2015 01 2015 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $10,705 $20,000 Implemented
OR0655 # 02 Y:2015 02 2015 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $4,161 $1,000 Implemented