Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
325
matching recommendationsSIC | 20 | Food and Kindred Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UL0115 # 05 Y:1994 | 05 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $132 | $346 | Implemented |
UL0115 # 03 Y:1994 | 03 | 1994 | INSTALL SMALLER BOILER (INCREASE HIGH FIRE DUTY CYCLE) | $4,013 | $4,000 | Implemented |
UL0115 # 02 Y:1994 | 02 | 1994 | COVER OPEN TANKS | $583 | $330 | Implemented |
OR0225 # 04 Y:1994 | 04 | 1994 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $18,649 | $500 | Implemented |
GT0543 # 02 Y:1994 | 02 | 1994 | INCREASE AMOUNT OF CONDENSATE RETURNED | $10,138 | $3,400 | Implemented |
GT0543 # 05 Y:1994 | 05 | 1994 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,940 | $5,000 | Implemented |
GT0543 # 04 Y:1994 | 04 | 1994 | RECOVER HEAT FROM EXHAUSTED STEAM, HOT AIR OR HOT WATER | $5,880 | $8,250 | Implemented |
GT0543 # 06 Y:1994 | 06 | 1994 | USE COMPRESSOR AIR FILTERS | $815 | $750 | Implemented |
UL0113 # 01 Y:1994 | 01 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,011 | $1,253 | Implemented |
UL0113 # 02 Y:1994 | 02 | 1994 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,294 | $1,500 | Implemented |
UL0113 # 03 Y:1994 | 03 | 1994 | COVER OPEN TANKS | $2,574 | $3,994 | Implemented |
NV0011 # 08 Y:1994 | 08 | 1994 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $4,913 | $292 | Implemented |
NV0011 # 03 Y:1994 | 03 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,918 | $-59 | Implemented |
NV0011 # 04 Y:1994 | 04 | 1994 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $478 | $120 | Implemented |
NV0011 # 01 Y:1994 | 01 | 1994 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $3,264 | $-3,025 | Implemented |
NV0011 # 06 Y:1994 | 06 | 1994 | RECOVER WASTE HEAT FROM EQUIPMENT | $11,100 | $1,400 | Implemented |
NV0011 # 02 Y:1994 | 02 | 1994 | OPTIMIZE PLANT POWER FACTOR | $1,387 | $3,600 | Implemented |
GT0541 # 02 Y:1994 | 02 | 1994 | USE DIRECT FLAME IMPINGEMENT OR INFRARED PROCESSING FOR CHAMBER TYPE HEATING | $31,280 | $94,500 | Implemented |
GT0541 # 01 Y:1994 | 01 | 1994 | PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER | $66,555 | $85,000 | Implemented |
UL0111 # 02 Y:1994 | 02 | 1994 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $4,373 | $9,840 | Implemented |
UL0111 # 01 Y:1994 | 01 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $665 | $1,324 | Implemented |
OR0221 # 03 Y:1994 | 03 | 1994 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $137 | $317 | Implemented |
OR0221 # 02 Y:1994 | 02 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $834 | $1,840 | Implemented |
SF0042 # 01 Y:1994 | 01 | 1994 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $2,464 | $1,647 | Implemented |
SF0042 # 05 Y:1994 | 05 | 1994 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $440 | $68 | Implemented |