Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Georgia Institute of Technology |
---|---|
Assessment Year | 1994 |
Principal Product | Ice Cream Cones |
NAICS | n/a |
SIC | 2052 - Cookies And Crackers |
Sales | $5,000,000-$10,000,000 |
# of Employees | 70 |
Plant Area (Sq.Ft.) | 102,239 |
Annual Production | 190,000,000 Pieces |
Production Hrs. Annual | 5,600 |
Location (State) | GA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $105,168 | 1,518,171 | kWh | $0.07 |
Natural Gas | $166,966 | 29,020 | MMBtu | $5.75 |
TOTAL ENERGY COSTS | $272,134 | |||
RECOMMENDED SAVINGS* | $111,950 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $97,835 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Administrative Changes | Electricity Usage | Natural Gas | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.8113 PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER |
Savings: $66,555 Cost: $85,000 |
- | - | - | - | $66,555 | - |
- - kWh |
- - MMBtu |
$66,555 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.5113 USE DIRECT FLAME IMPINGEMENT OR INFRARED PROCESSING FOR CHAMBER TYPE HEATING |
Savings: $31,280 Cost: $94,500 |
- | - | $31,280 | 5,440 | - | - |
- - kWh |
$31,280 5,440 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $7,245 Cost: $5,000 |
- | - | $7,245 | 1,260 | - | - |
- - kWh |
$7,245 1,260 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $3,910 Cost: $9,240 |
$3,910 | 56,565 | - | - | - | - |
$3,910 56,565 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $2,960 Cost: $17,150 |
$2,960 | 43,083 | - | - | - | - |
$2,960 43,083 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $111,950 Cost: $210,890 |
$6,870 | 99,648 | $38,525 | 6,700 | $66,555 | - | $6,870 99,648 kWh |
$38,525 6,700 MMBtu |
$66,555 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $97,835 Cost: $179,500 |
- | - | $31,280 | 5,440 | $66,555 | - | - - kWh |
$31,280 5,440 MMBtu |
$66,555 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Administrative Changes | Electricity Usage | Natural Gas | Administrative Changes |