Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
20,785
matching recommendationsSIC | 20 | Food and Kindred Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MU0025 # 05 Y:2023 | 05 | 2023 | USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE | $382 | $690 | Not Implemented |
MU0025 # 06 Y:2023 | 06 | 2023 | USE OPTIMUM TEMPERATURE | $1,361 | $0 | Implemented |
MU0025 # 07 Y:2023 | 07 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,434 | $2,876 | Implemented |
MU0025 # 08 Y:2023 | 08 | 2023 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $431 | $0 | Implemented |
MU0025 # 09 Y:2023 | 09 | 2023 | USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE | $13,952 | $19,852 | Implemented |
MU0025 # 10 Y:2023 | 10 | 2023 | RECOVER WASTE HEAT FROM EQUIPMENT | $2,348 | $9,576 | Not Implemented |
IC0278 # 01 Y:2023 | 01 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $147,541 | $1,271,712 | Not Implemented |
IC0278 # 02 Y:2023 | 02 | 2023 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT INCOMING FLUIDS | $5,879 | $15,415 | Not Implemented |
IC0278 # 03 Y:2023 | 03 | 2023 | USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT | $175,901 | $710,922 | Not Implemented |
IC0278 # 04 Y:2023 | 04 | 2023 | ELIMINATE LEAKS IN WATER LINES AND VALVES | $5,040 | $600 | Implemented |
IP0172 # 01 Y:2023 | 01 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $8,640 | $132 | Not Implemented |
IP0172 # 02 Y:2023 | 02 | 2023 | INSTALL OR UPGRADE INSULATION ON HVAC DISTRIBUTION SYSTEMS | $512 | $83 | Not Implemented |
IP0172 # 03 Y:2023 | 03 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,870 | $1,313 | Not Implemented |
IP0172 # 04 Y:2023 | 04 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $14,315 | $14,588 | Not Implemented |
IP0172 # 05 Y:2023 | 05 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $7,584 | $8,088 | Not Implemented |
NT0005 # 01 Y:2023 | 01 | 2023 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $6,885 | $1,258 | Not Implemented |
NT0005 # 02 Y:2023 | 02 | 2023 | ADJUST / MAINTAIN FORK LIFT TRUCKS FOR MOST EFFICIENT OPERATION | $6,240 | $0 | Not Implemented |
NT0005 # 03 Y:2023 | 03 | 2023 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $832,000 | $100,000 | Not Implemented |
NT0005 # 04 Y:2023 | 04 | 2023 | CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD | $4,375 | $6,539 | Not Implemented |
NT0005 # 05 Y:2023 | 05 | 2023 | OPTIMIZE PLANT POWER FACTOR | $4,433 | $9,008 | Not Implemented |
NT0005 # 06 Y:2023 | 06 | 2023 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $2,810 | $0 | Not Implemented |
MS0413 # 01 Y:2023 | 01 | 2023 | INSTALL OCCUPANCY SENSORS | $225 | $341 | n/a |
MS0413 # 02 Y:2023 | 02 | 2023 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $1,194 | $17,530 | n/a |
MS0413 # 03 Y:2023 | 03 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $35,830 | $456,750 | n/a |
MS0413 # 04 Y:2023 | 04 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,019 | $1,523 | n/a |