Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
233
matching recommendationsSIC | 20 | Food and Kindred Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UU0114 # 04 Y:2017 | 04 | 2017 | REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC | $2,795 | $1,315 | Not Implemented |
UU0114 # 05 Y:2017 | 05 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $17,973 | $39,045 | Implemented |
UU0114 # 06 Y:2017 | 06 | 2017 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $5,345 | $0 | Implemented |
BS0085 # 01 Y:2016 | 01 | 2016 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $679 | $2,240 | Not Implemented |
BS0085 # 02 Y:2016 | 02 | 2016 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $736 | $390 | Not Implemented |
BS0085 # 03 Y:2016 | 03 | 2016 | PAY UTILITY BILLS ON TIME | $348 | $108 | Not Implemented |
BS0085 # 04 Y:2016 | 04 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $276 | $607 | Not Implemented |
BS0085 # 05 Y:2016 | 05 | 2016 | OPTIMIZE PLANT POWER FACTOR | $11,091 | $13,382 | Not Implemented |
BS0085 # 06 Y:2016 | 06 | 2016 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $974 | $528 | Not Implemented |
BS0085 # 07 Y:2016 | 07 | 2016 | UPGRADE CONTROLS ON COMPRESSORS | $1,036 | $2,249 | Not Implemented |
BS0085 # 08 Y:2016 | 08 | 2016 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $145 | $600 | Not Implemented |
BS0085 # 09 Y:2016 | 09 | 2016 | ELIMINATE LEAKS IN WATER LINES AND VALVES | $139 | $16 | Not Implemented |
BS0085 # 10 Y:2016 | 10 | 2016 | UPGRADE OBSOLETE EQUIPMENT | $15,075 | $16,355 | Not Implemented |
BS0085 # 11 Y:2016 | 11 | 2016 | INSULATE FEEDWATER TANK | $291 | $565 | Not Implemented |
AM0654 # 01 Y:2014 | 01 | 2014 | OPTIMIZE PLANT POWER FACTOR | $6,620 | $9,320 | Implemented |
AM0654 # 02 Y:2014 | 02 | 2014 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $2,950 | $1,320 | Implemented |
AM0654 # 03 Y:2014 | 03 | 2014 | REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT | $2,037 | $4,000 | Not Implemented |
AM0654 # 04 Y:2014 | 04 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,492 | $3,750 | Implemented |
AM0654 # 05 Y:2014 | 05 | 2014 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,476 | $1,000 | Implemented |
AM0654 # 06 Y:2014 | 06 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $724 | $576 | Implemented |
AM0654 # 07 Y:2014 | 07 | 2014 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $677 | $5 | Implemented |
AM0654 # 08 Y:2014 | 08 | 2014 | INSTALL OCCUPANCY SENSORS | $217 | $400 | Implemented |
UU0101 # 01 Y:2006 | 01 | 2006 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $16,190 | $10,000 | Not Implemented |
UU0101 # 02 Y:2006 | 02 | 2006 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,280 | $4,150 | Not Implemented |
UU0101 # 03 Y:2006 | 03 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,230 | $3,050 | Not Implemented |