Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
466
matching recommendationsSIC | 20 | Food and Kindred Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
TR0044 # 03 Y:2022 | 03 | 2022 | USE SOLAR HEAT TO MAKE ELECTRICTY | $109,638 | $1,599,426 | Not Implemented |
TR0044 # 02 Y:2022 | 02 | 2022 | INSTALL OCCUPANCY SENSORS | $921 | $260 | Implemented |
TR0044 # 04 Y:2022 | 04 | 2022 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $8,106 | $2,500 | Implemented |
TR0044 # 01 Y:2022 | 01 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $363 | $1,726 | Implemented |
TR0042 # 03 Y:2022 | 03 | 2022 | REDUCE INFILTRATION TO REFRIGERATED AREAS; ISOLATE HOT EQUIPMENT FROM REFRIGERATED AREAS | $18,544 | $6,243 | Implemented |
TR0042 # 02 Y:2022 | 02 | 2022 | USE SOLAR HEAT TO MAKE ELECTRICTY | $33,568 | $395,038 | Not Implemented |
TR0042 # 01 Y:2022 | 01 | 2022 | INSTALL OCCUPANCY SENSORS | $141 | $52 | Implemented |
CC0012 # 05 Y:2022 | 05 | 2022 | MODERATE COOLING TOWER OUTLET TEMPERATURE | $3,233 | $0 | n/a |
CC0012 # 01 Y:2022 | 01 | 2022 | UPGRADE CONTROLS ON COMPRESSORS | $38,944 | $0 | n/a |
CC0012 # 03 Y:2022 | 03 | 2022 | OPERATE BOILERS ON HIGH FIRE SETTING | $4,544 | $10,000 | n/a |
CC0012 # 02 Y:2022 | 02 | 2022 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $18,525 | $10,000 | n/a |
CC0012 # 04 Y:2022 | 04 | 2022 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $12,343 | $16,000 | n/a |
CC0012 # 06 Y:2022 | 06 | 2022 | REPLACE PURCHASED STEAM WITH OTHER ENERGY SOURCE | $7,230 | $30,000 | n/a |
CC0012 # 07 Y:2022 | 07 | 2022 | USE FLUE GASES TO HEAT PROCESS OR SERVICE WATER | $47,241 | $125,000 | n/a |
MI0417 # 02 Y:2022 | 02 | 2022 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $25,845 | $0 | Implemented |
MI0417 # 06 Y:2022 | 06 | 2022 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $6,907 | $580 | Not Implemented |
MI0417 # 04 Y:2022 | 04 | 2022 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $10,521 | $4,259 | Not Implemented |
MI0417 # 03 Y:2022 | 03 | 2022 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $12,705 | $18,960 | Not Implemented |
MI0417 # 07 Y:2022 | 07 | 2022 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $2,772 | $2,740 | Not Implemented |
MI0417 # 08 Y:2022 | 08 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,839 | $2,140 | Implemented |
MI0417 # 05 Y:2022 | 05 | 2022 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $9,078 | $12,846 | Not Implemented |
MI0417 # 01 Y:2022 | 01 | 2022 | UPGRADE CONTROLS ON COMPRESSORS | $58,143 | $16,338 | Not Implemented |
CM1010 # 02 Y:2022 | 02 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,190 | $17,940 | Implemented |
CM1010 # 07 Y:2022 | 07 | 2022 | TURN OFF EQUIPMENT WHEN NOT IN USE | $14,400 | $0 | Not Implemented |
CM1010 # 06 Y:2022 | 06 | 2022 | IMPROVE HANDLING PRACTICES | $1,056 | $9,800 | Implemented |