Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,407
matching recommendationsSIC | 2013 | Sausages And Other Prepared Meats |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
NL0064 # 02 Y:2022 | 02 | 2022 | INSULATE BARE EQUIPMENT | $1,251 | $1,729 | Implemented |
NL0064 # 06 Y:2022 | 06 | 2022 | INSULATE BARE EQUIPMENT | $204 | $130 | Implemented |
NL0064 # 01 Y:2022 | 01 | 2022 | USE DECANTING, FLOTATION TO REMOVE CONTAMINANTS | $79,442 | $292,000 | Implemented |
TT0260 # 03 Y:2021 | 03 | 2021 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,928 | $300 | Not Implemented |
TT0260 # 01 Y:2021 | 01 | 2021 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $12,890 | $3,640 | Not Implemented |
TT0260 # 08 Y:2021 | 08 | 2021 | INSTALL OCCUPANCY SENSORS | $401 | $553 | Implemented |
TT0260 # 04 Y:2021 | 04 | 2021 | REPLACE TREATED WATER WITH WELL / SURFACE WATER | $4,069 | $16,500 | Not Implemented |
TT0260 # 02 Y:2021 | 02 | 2021 | OPTIMIZE PLANT POWER FACTOR | $10,005 | $10,000 | Not Implemented |
TT0260 # 05 Y:2021 | 05 | 2021 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,791 | $1,660 | Not Implemented |
TT0260 # 07 Y:2021 | 07 | 2021 | INSULATE BARE EQUIPMENT | $783 | $700 | Implemented |
TT0260 # 06 Y:2021 | 06 | 2021 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $1,508 | $3,500 | Not Implemented |
SF0573 # 03 Y:2021 | 03 | 2021 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $514 | $105 | Implemented |
SF0573 # 02 Y:2021 | 02 | 2021 | TURN OFF EQUIPMENT WHEN NOT IN USE | $4,133 | $0 | Implemented |
SF0573 # 01 Y:2021 | 01 | 2021 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $718 | $0 | Implemented |
SF0573 # 05 Y:2021 | 05 | 2021 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,292 | $4,273 | Implemented |
SF0573 # 06 Y:2021 | 06 | 2021 | USE SOLAR HEAT TO MAKE ELECTRICTY | $56,800 | $266,176 | Implemented |
SF0573 # 04 Y:2021 | 04 | 2021 | USE FLUE GASES TO HEAT PROCESS OR SERVICE WATER | $1,654 | $960 | Not Implemented |
LE0508 # 01 Y:2021 | 01 | 2021 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,328 | $100 | Implemented |
LE0508 # 05 Y:2021 | 05 | 2021 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $5,407 | $24,000 | Implemented |
LE0508 # 03 Y:2021 | 03 | 2021 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $7,110 | $10,000 | Implemented |
LE0508 # 02 Y:2021 | 02 | 2021 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $23,709 | $29,000 | Not Implemented |
LE0508 # 04 Y:2021 | 04 | 2021 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,625 | $3,000 | Implemented |
GT0943 # 01 Y:2020 | 01 | 2020 | INSTALL TIMERS AND/OR THERMOSTATS | $3,005 | $563 | Implemented |
GT0943 # 02 Y:2020 | 02 | 2020 | INSTALL OCCUPANCY SENSORS | $4,323 | $2,678 | Implemented |
GT0943 # 03 Y:2020 | 03 | 2020 | TURN OFF EQUIPMENT WHEN NOT IN USE | $490 | $350 | Not Implemented |