Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
718
matching recommendationsSIC | 2015 | Poultry Slaughtering And Processing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OK0849 # 05 Y:2013 | 05 | 2013 | INSTALL / REPAIR INSULATION ON STEAM LINES | $30,500 | $24,400 | Not Implemented |
OK0849 # 06 Y:2013 | 06 | 2013 | ESTABLISH BURNER MAINTENANCE SCHEDULE FOR BOILERS | $1,100 | $1,850 | Not Implemented |
OK0849 # 07 Y:2013 | 07 | 2013 | REDUCE EXCESSIVE BOILER BLOWDOWN | $18,700 | $29,260 | Not Implemented |
OK0849 # 08 Y:2013 | 08 | 2013 | ESTABLISH BURNER MAINTENANCE SCHEDULE FOR BOILERS | $9,409 | $18,800 | Not Implemented |
OK0849 # 09 Y:2013 | 09 | 2013 | UPGRADE CONTROLS ON COMPRESSORS | $26,916 | $53,800 | Not Implemented |
OK0849 # 10 Y:2013 | 10 | 2013 | REDUCE EXCESSIVE BOILER BLOWDOWN | $27,300 | $18,000 | Not Implemented |
OK0833 # 01 Y:2012 | 01 | 2012 | REDUCE COMBUSTION AIR FLOW TO OPTIMUM | $5,700 | $5,000 | Implemented |
OK0833 # 02 Y:2012 | 02 | 2012 | INSULATE BARE EQUIPMENT | $4,000 | $2,000 | Not Implemented |
OK0833 # 03 Y:2012 | 03 | 2012 | INSULATE BARE EQUIPMENT | $1,600 | $2,500 | Not Implemented |
OK0833 # 04 Y:2012 | 04 | 2012 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,000 | $500 | Implemented |
OK0833 # 05 Y:2012 | 05 | 2012 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,800 | $4,050 | Not Implemented |
OK0833 # 06 Y:2012 | 06 | 2012 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $1,900 | $14,000 | Not Implemented |
OK0833 # 07 Y:2012 | 07 | 2012 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $10,150 | $24,000 | Not Implemented |
OK0833 # 08 Y:2012 | 08 | 2012 | LOWER COMPRESSOR PRESSURE THROUGH A/C SYSTEM MODIFICATION | $31,700 | $0 | Implemented |
OK0833 # 09 Y:2012 | 09 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $460 | $3,400 | Implemented |
UK1210 # 01 Y:2012 | 01 | 2012 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $11,568 | $12,500 | Not Implemented |
UK1210 # 02 Y:2012 | 02 | 2012 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $7,955 | $5,000 | Not Implemented |
UK1210 # 03 Y:2012 | 03 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,598 | $2,240 | Not Implemented |
UK1210 # 04 Y:2012 | 04 | 2012 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $4,202 | $500 | Not Implemented |
UK1210 # 05 Y:2012 | 05 | 2012 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $1,591 | $1,000 | Not Implemented |
UK1210 # 06 Y:2012 | 06 | 2012 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $521 | $180 | Not Implemented |
UK1210 # 07 Y:2012 | 07 | 2012 | RECOVER WASTE HEAT FROM EQUIPMENT | $52,633 | $52,000 | Not Implemented |
UK1210 # 08 Y:2012 | 08 | 2012 | KEEP BOILER TUBES CLEAN | $6,493 | $2,410 | Not Implemented |
UK1210 # 09 Y:2012 | 09 | 2012 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $4,708 | $100 | Not Implemented |
UK1210 # 10 Y:2012 | 10 | 2012 | INSTALL / REPAIR INSULATION ON STEAM LINES | $1,990 | $1,060 | Not Implemented |