Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
2,779
matching recommendationsSIC | 202 | Dairy Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OK0704 # 08 Y:2005 | 08 | 2005 | INSTALL SET-BACK TIMERS | $1,663 | $20 | Not Implemented |
OK0704 # 09 Y:2005 | 09 | 2005 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $1,463 | $13,554 | Not Implemented |
OK0704 # 10 Y:2005 | 10 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $165 | $1,153 | Not Implemented |
MI0101 # 01 Y:2005 | 01 | 2005 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $51,010 | $72,500 | Not Implemented |
MI0101 # 02 Y:2005 | 02 | 2005 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $12,178 | $180 | Implemented |
MI0101 # 03 Y:2005 | 03 | 2005 | RECOVER WASTE HEAT FROM EQUIPMENT | $7,508 | $3,000 | Not Implemented |
MI0101 # 04 Y:2005 | 04 | 2005 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $4,336 | $600 | Not Implemented |
MI0101 # 05 Y:2005 | 05 | 2005 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $2,200 | $6,660 | Implemented |
MI0101 # 06 Y:2005 | 06 | 2005 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,386 | $1,030 | Implemented |
MI0101 # 07 Y:2005 | 07 | 2005 | INSULATE BARE EQUIPMENT | $294 | $195 | Not Implemented |
OR0479 # 01 Y:2005 | 01 | 2005 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $116,320 | $115,000 | Implemented |
OR0479 # 02 Y:2005 | 02 | 2005 | TURN OFF EQUIPMENT WHEN NOT IN USE | $19,750 | $100 | Implemented |
OR0479 # 03 Y:2005 | 03 | 2005 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $6,710 | $800 | Implemented |
OR0479 # 04 Y:2005 | 04 | 2005 | MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE | $1,500 | $0 | Not Implemented |
OR0479 # 05 Y:2005 | 05 | 2005 | MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE | $700 | $0 | Not Implemented |
MI0099 # 01 Y:2005 | 01 | 2005 | REPLACE BOILER | $31,718 | $82,200 | Implemented |
MI0099 # 02 Y:2005 | 02 | 2005 | USE OPTIMUM SIZE AND CAPACITY EQUIPMENT | $16,520 | $7,062 | Not Implemented |
MI0099 # 03 Y:2005 | 03 | 2005 | UPGRADE CONTROLS ON COMPRESSORS | $11,973 | $2,750 | Implemented |
MI0099 # 04 Y:2005 | 04 | 2005 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $8,746 | $4,736 | Not Implemented |
MI0099 # 05 Y:2005 | 05 | 2005 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,897 | $470 | Implemented |
MI0099 # 06 Y:2005 | 06 | 2005 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,355 | $1,750 | Implemented |
MI0099 # 07 Y:2005 | 07 | 2005 | USE MINIMUM STEAM OPERATING PRESSURE | $200 | $115 | Implemented |
AS0394 # 01 Y:2005 | 01 | 2005 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,769 | $3,632 | Not Implemented |
AS0394 # 02 Y:2005 | 02 | 2005 | DIRECT WARMEST AIR TO COMBUSTION INTAKE | $18,219 | $1,000 | Not Implemented |
AS0394 # 03 Y:2005 | 03 | 2005 | INSTALL / REPAIR INSULATION ON STEAM LINES | $1,961 | $321 | Not Implemented |