Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
170
matching recommendationsSIC | 202 | Dairy Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
CO0559 # 01 Y:2004 | 01 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $7,070 | $440 | Implemented |
CO0559 # 06 Y:2004 | 06 | 2004 | INSTALL OCCUPANCY SENSORS | $1,760 | $2,260 | Implemented |
CO0559 # 08 Y:2004 | 08 | 2004 | INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS | $650 | $4,550 | Not Implemented |
CO0559 # 05 Y:2004 | 05 | 2004 | INSULATE BARE EQUIPMENT | $710 | $1,790 | Implemented |
CO0559 # 07 Y:2004 | 07 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $572 | $292 | Implemented |
CO0559 # 03 Y:2004 | 03 | 2004 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $1,190 | $740 | Implemented |
CO0559 # 02 Y:2004 | 02 | 2004 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $355 | $416 | Implemented |
CO0559 # 04 Y:2004 | 04 | 2004 | UTILIZE OUTSIDE AIR INSTEAD OF CONDITIONED AIR FOR DRYING | $1,180 | $810 | Implemented |
LL0207 # 02 Y:2004 | 02 | 2004 | INSULATE BARE EQUIPMENT | $34,833 | $7,488 | Implemented |
LL0207 # 11 Y:2004 | 11 | 2004 | RECOVER AND REUSE COOLING WATER | $11,194 | $32,000 | Not Implemented |
LL0207 # 10 Y:2004 | 10 | 2004 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $46,500 | $3,150 | Implemented |
LL0207 # 09 Y:2004 | 09 | 2004 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $33 | $180 | Not Implemented |
LL0207 # 08 Y:2004 | 08 | 2004 | INSTALL OCCUPANCY SENSORS | $99 | $120 | Not Implemented |
LL0207 # 07 Y:2004 | 07 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $701 | $525 | Not Implemented |
LL0207 # 06 Y:2004 | 06 | 2004 | USE PHOTOCELL CONTROLS | $449 | $30 | Not Implemented |
LL0207 # 05 Y:2004 | 05 | 2004 | REPAIR AND ELIMINATE STEAM LEAKS | $2,149 | $1,960 | Implemented |
LL0207 # 04 Y:2004 | 04 | 2004 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $3,171 | $225 | Not Implemented |
LL0207 # 03 Y:2004 | 03 | 2004 | INCREASE AMOUNT OF CONDENSATE RETURNED | $6,837 | $12,236 | Not Implemented |
LL0207 # 01 Y:2004 | 01 | 2004 | PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT | $36,769 | $16,000 | Implemented |
SU0197 # 03 Y:2004 | 03 | 2004 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,966 | $0 | Implemented |
SU0197 # 02 Y:2004 | 02 | 2004 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $4,301 | $0 | Not Implemented |
SU0197 # 05 Y:2004 | 05 | 2004 | INSTALL TURBULATORS | $3,875 | $350 | Not Implemented |
SU0197 # 01 Y:2004 | 01 | 2004 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $16,106 | $0 | Not Implemented |
SU0197 # 06 Y:2004 | 06 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,462 | $725 | Implemented |
SU0197 # 04 Y:2004 | 04 | 2004 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $4,301 | $154 | Implemented |