Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
32
matching recommendationsSIC | 2026 | Fluid Milk |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UK1511 # 14 Y:2015 | 14 | 2015 | INSULATE FEEDWATER TANK | $1,113 | $862 | Implemented |
UK1511 # 13 Y:2015 | 13 | 2015 | INSTALL TURBULATORS | $8,026 | $9,000 | Not Implemented |
UK1511 # 12 Y:2015 | 12 | 2015 | PREHEAT COMBUSTION AIR WITH WASTE HEAT | $7,205 | $18,400 | Not Implemented |
UK1511 # 11 Y:2015 | 11 | 2015 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $552 | $0 | Implemented |
UK1511 # 10 Y:2015 | 10 | 2015 | USE ONLY CERTIFIED MOTOR REPAIR SHOPS | $2,199 | $1,865 | Not Implemented |
UK1511 # 09 Y:2015 | 09 | 2015 | UPGRADE OBSOLETE EQUIPMENT | $2,127 | $14,000 | Implemented |
UK1511 # 08 Y:2015 | 08 | 2015 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $737 | $1,500 | Implemented |
UK1511 # 07 Y:2015 | 07 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,050 | $0 | Implemented |
UK1511 # 06 Y:2015 | 06 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,159 | $1,371 | Implemented |
UK1511 # 05 Y:2015 | 05 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $24,582 | $51,370 | Implemented |
UK1511 # 04 Y:2015 | 04 | 2015 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $596 | $0 | Implemented |
UK1511 # 03 Y:2015 | 03 | 2015 | OPTIMIZE PLANT POWER FACTOR | $9,011 | $8,260 | Implemented |
UK1511 # 02 Y:2015 | 02 | 2015 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $42,293 | $0 | Not Implemented |
UK1511 # 01 Y:2015 | 01 | 2015 | USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT | $457,639 | $1,000,000 | Implemented |
SF0459 # 17 Y:2015 | 17 | 2015 | USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION | $166,472 | $100,519 | Implemented |
SF0459 # 18 Y:2015 | 18 | 2015 | USE POWER DURING OFF-PEAK PERIODS | $5,106 | $0 | Not Implemented |
SF0459 # 01 Y:2015 | 01 | 2015 | REPAIR OR REPLACE STEAM TRAPS | $29,918 | $5,047 | Implemented |
SF0459 # 16 Y:2015 | 16 | 2015 | INSTALL OCCUPANCY SENSORS | $6,651 | $23,688 | Not Implemented |
SF0459 # 15 Y:2015 | 15 | 2015 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $14,707 | $39,862 | Not Implemented |
SF0459 # 14 Y:2015 | 14 | 2015 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $42,975 | $82,916 | Implemented |
SF0459 # 13 Y:2015 | 13 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $14,158 | $24,030 | Implemented |
SF0459 # 12 Y:2015 | 12 | 2015 | USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY | $58,197 | $81,522 | Implemented |
SF0459 # 11 Y:2015 | 11 | 2015 | USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY | $17,754 | $22,786 | Implemented |
SF0459 # 10 Y:2015 | 10 | 2015 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $5,935 | $5,491 | Not Implemented |
SF0459 # 09 Y:2015 | 09 | 2015 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $7,959 | $6,271 | Not Implemented |