Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
909
matching recommendationsSIC | 2033 | Canned Fruits And Vegetables |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OR0243 # 04 Y:1995 | 04 | 1995 | PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT | $2,714 | $2,108 | Not Implemented |
OR0243 # 05 Y:1995 | 05 | 1995 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $278 | $796 | Implemented |
SD0127 # 01 Y:1995 | 01 | 1995 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $3,637 | $5,890 | Implemented |
SD0127 # 02 Y:1995 | 02 | 1995 | USE COOLING TOWER WATER INSTEAD OF REFRIGERATION | $18,822 | $32,000 | Implemented |
SD0127 # 03 Y:1995 | 03 | 1995 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $914 | $16 | Implemented |
SD0127 # 04 Y:1995 | 04 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,145 | $7,922 | Implemented |
SD0127 # 05 Y:1995 | 05 | 1995 | INSTALL SPECTRAL REFLECTORS / DELAMP | $11,158 | $13,280 | Implemented |
SD0127 # 06 Y:1995 | 06 | 1995 | INSTALL OCCUPANCY SENSORS | $3,379 | $2,569 | Implemented |
OR0235 # 01 Y:1995 | 01 | 1995 | ADD AREA LIGHTING SWITCHES | $2,089 | $2,200 | Implemented |
OR0235 # 02 Y:1995 | 02 | 1995 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $2,052 | $2,592 | Implemented |
OR0235 # 03 Y:1995 | 03 | 1995 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $250 | $500 | Implemented |
OR0235 # 04 Y:1995 | 04 | 1995 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,680 | $4,000 | Implemented |
OR0235 # 05 Y:1995 | 05 | 1995 | USE MULTIPLE-EFFECT EVAPORATORS | $2,900 | $9,500 | Implemented |
OR0235 # 06 Y:1995 | 06 | 1995 | MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE | $1,970 | $8,500 | Not Implemented |
OK0457 # 01 Y:1995 | 01 | 1995 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $7,236 | $13,720 | Not Implemented |
OK0457 # 02 Y:1995 | 02 | 1995 | DIRECT WARMEST AIR TO COMBUSTION INTAKE | $2,691 | $64 | Implemented |
OK0457 # 03 Y:1995 | 03 | 1995 | INSTALL / REPAIR INSULATION ON STEAM LINES | $1,741 | $4,508 | Implemented |
OK0457 # 04 Y:1995 | 04 | 1995 | INSULATE BARE EQUIPMENT | $1,344 | $3,612 | Implemented |
OK0457 # 05 Y:1995 | 05 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,224 | $2,077 | Implemented |
OK0457 # 06 Y:1995 | 06 | 1995 | INSULATE BARE EQUIPMENT | $882 | $2,480 | Not Implemented |
OK0457 # 07 Y:1995 | 07 | 1995 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $199 | $240 | Implemented |
OK0457 # 08 Y:1995 | 08 | 1995 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $49 | $76 | Implemented |
UL0115 # 01 Y:1994 | 01 | 1994 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $472 | $1,520 | Not Implemented |
UL0115 # 02 Y:1994 | 02 | 1994 | COVER OPEN TANKS | $583 | $330 | Implemented |
UL0115 # 03 Y:1994 | 03 | 1994 | INSTALL SMALLER BOILER (INCREASE HIGH FIRE DUTY CYCLE) | $4,013 | $4,000 | Implemented |