IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

23

matching recommendations
Reset
SIC 2048 Prepared Feeds, Nec
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
NL0021 # 03 Y:2018 03 2018 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $335 $1,000 Implemented
NL0021 # 02 Y:2018 02 2018 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,774 $15,206 Implemented
NL0021 # 01 Y:2018 01 2018 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $12,355 $0 Implemented
NL0013 # 07 Y:2017 07 2017 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $133 $110 Not Implemented
NL0013 # 06 Y:2017 06 2017 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $309 $111 Not Implemented
NL0013 # 05 Y:2017 05 2017 INSTALL / REPAIR INSULATION ON STEAM LINES $485 $273 Not Implemented
NL0013 # 04 Y:2017 04 2017 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $668 $0 Not Implemented
NL0013 # 03 Y:2017 03 2017 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,676 $452 Implemented
NL0013 # 02 Y:2017 02 2017 INSULATE BARE EQUIPMENT $6,000 $16,000 Implemented
NL0013 # 01 Y:2017 01 2017 RECOVER AND REUSE WASTE MATERIAL $6,493 $7,000 Not Implemented
KU0543 # 07 Y:2000 07 2000 USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION $5,630 $8,000 Not Implemented
KU0543 # 08 Y:2000 08 2000 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK $56,920 $70,000 Not Implemented
KU0543 # 06 Y:2000 06 2000 ELIMINATE A BY-PRODUCT $7,940 $9,680 Not Implemented
KU0543 # 05 Y:2000 05 2000 REDUCE INFILTRATION TO REFRIGERATED AREAS; ISOLATE HOT EQUIPMENT FROM REFRIGERATED AREAS $420 $100 Implemented
KU0543 # 04 Y:2000 04 2000 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $430 $50 Implemented
KU0543 # 03 Y:2000 03 2000 INSTALL OCCUPANCY SENSORS $430 $450 Not Implemented
KU0543 # 02 Y:2000 02 2000 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $25,020 $50,000 Not Implemented
KU0543 # 01 Y:2000 01 2000 PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER $27,200 $0 Implemented
CO0451 # 01 Y:1999 01 1999 INSTALL / REPAIR INSULATION ON STEAM LINES $7,190 $6,250 Not Implemented
CO0451 # 05 Y:1999 05 1999 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $20 $0 Not Implemented
CO0451 # 04 Y:1999 04 1999 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $190 $320 Implemented
CO0451 # 03 Y:1999 03 1999 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $220 $20 Implemented
CO0451 # 02 Y:1999 02 1999 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $4,080 $4,000 Implemented