Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
105
matching recommendationsSIC | 205 | Bakery Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
GT0541 # 04 Y:1994 | 04 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,910 | $9,240 | Not Implemented |
GT0541 # 05 Y:1994 | 05 | 1994 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $2,960 | $17,150 | Not Implemented |
GT0541 # 03 Y:1994 | 03 | 1994 | RECOVER WASTE HEAT FROM EQUIPMENT | $7,245 | $5,000 | Not Implemented |
GT0541 # 02 Y:1994 | 02 | 1994 | USE DIRECT FLAME IMPINGEMENT OR INFRARED PROCESSING FOR CHAMBER TYPE HEATING | $31,280 | $94,500 | Implemented |
GT0541 # 01 Y:1994 | 01 | 1994 | PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER | $66,555 | $85,000 | Implemented |
SF0042 # 02 Y:1994 | 02 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,820 | $10,676 | Implemented |
SF0042 # 04 Y:1994 | 04 | 1994 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $8,759 | $1,349 | Not Implemented |
SF0042 # 03 Y:1994 | 03 | 1994 | TURN OFF EQUIPMENT WHEN NOT IN USE | $1,004 | $0 | Implemented |
SF0042 # 01 Y:1994 | 01 | 1994 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $2,464 | $1,647 | Implemented |
SF0042 # 05 Y:1994 | 05 | 1994 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $440 | $68 | Implemented |
DS0014 # 04 Y:1994 | 04 | 1994 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $301 | $168 | Implemented |
DS0014 # 01 Y:1994 | 01 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $20,856 | $14,991 | Implemented |
DS0014 # 02 Y:1994 | 02 | 1994 | INSTALL OCCUPANCY SENSORS | $2,822 | $11,013 | Implemented |
DS0014 # 06 Y:1994 | 06 | 1994 | INSULATE BARE EQUIPMENT | $10,869 | $2,424 | Implemented |
DS0014 # 05 Y:1994 | 05 | 1994 | RECOVER WASTE HEAT FROM EQUIPMENT | $2,980 | $4,080 | Not Implemented |
DS0014 # 03 Y:1994 | 03 | 1994 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $3,370 | $4,329 | Implemented |
AS0128 # 10 Y:1994 | 10 | 1994 | INSTALL / REPAIR INSULATION ON STEAM LINES | $1,668 | $554 | Implemented |
AS0128 # 09 Y:1994 | 09 | 1994 | INSTALL / REPAIR INSULATION ON CONDENSATE LINES | $826 | $975 | Not Implemented |
AS0128 # 07 Y:1994 | 07 | 1994 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $459 | $1,522 | Implemented |
AS0127 # 06 Y:1994 | 06 | 1994 | INSTALL OCCUPANCY SENSORS | $191 | $300 | Implemented |
AS0127 # 07 Y:1994 | 07 | 1994 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $1,575 | $750 | Implemented |
AS0128 # 01 Y:1994 | 01 | 1994 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $7,829 | $4,753 | Implemented |
AS0128 # 02 Y:1994 | 02 | 1994 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $490 | $0 | Implemented |
AS0128 # 03 Y:1994 | 03 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,393 | $12,076 | Not Implemented |
AS0128 # 04 Y:1994 | 04 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $175 | $300 | Not Implemented |