Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
19
matching recommendationsSIC | 2052 | Cookies And Crackers |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
WI0063 # 03 Y:1989 | 03 | 1989 | INSTALL TIMERS AND/OR THERMOSTATS | $2,768 | $1,750 | Implemented |
WI0063 # 12 Y:1989 | 12 | 1989 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $584 | $1,978 | Not Implemented |
WI0063 # 11 Y:1989 | 11 | 1989 | RECOVER WASTE HEAT FROM EQUIPMENT | $740 | $1,000 | Not Implemented |
WI0063 # 10 Y:1989 | 10 | 1989 | INSTALL SET-BACK TIMERS | $929 | $400 | Not Implemented |
WI0063 # 09 Y:1989 | 09 | 1989 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,100 | $2,000 | Not Implemented |
WI0063 # 08 Y:1989 | 08 | 1989 | IMPROVE LUBRICATION PRACTICES | $1,606 | $0 | Not Implemented |
WI0063 # 07 Y:1989 | 07 | 1989 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $992 | $1,043 | Implemented |
WI0063 # 06 Y:1989 | 06 | 1989 | USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE | $1,822 | $5,000 | Not Implemented |
WI0063 # 05 Y:1989 | 05 | 1989 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $2,658 | $4,000 | Implemented |
WI0063 # 04 Y:1989 | 04 | 1989 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $3,284 | $1,040 | Implemented |
WI0063 # 02 Y:1989 | 02 | 1989 | RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR | $8,040 | $15,000 | Not Implemented |
WI0063 # 01 Y:1989 | 01 | 1989 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $10,384 | $0 | Implemented |
TN0373 # 01 Y:1989 | 01 | 1989 | OPERATE BOILERS ON HIGH FIRE SETTING | $11,558 | $20,160 | Implemented |
TN0373 # 07 Y:1989 | 07 | 1989 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,407 | $540 | Implemented |
TN0373 # 06 Y:1989 | 06 | 1989 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,599 | $1,800 | Implemented |
TN0373 # 05 Y:1989 | 05 | 1989 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $46 | $0 | Implemented |
TN0373 # 04 Y:1989 | 04 | 1989 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,164 | $180 | Implemented |
TN0373 # 03 Y:1989 | 03 | 1989 | KEEP LAMPS AND REFLECTORS CLEAN | $8,465 | $12,145 | Not Implemented |
TN0373 # 02 Y:1989 | 02 | 1989 | USE RADIANT HEATER FOR SPOT HEATING | $7,050 | $11,350 | Implemented |