Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
36
matching recommendationsSIC | 208 | Beverages |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OR0777 # 03 Y:2023 | 03 | 2023 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $2,570 | $0 | Implemented |
OR0777 # 02 Y:2023 | 02 | 2023 | INSTALL COMMON HEADER ON COMPRESSORS | $2,832 | $6,989 | Implemented |
OR0777 # 01 Y:2023 | 01 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $8,479 | $0 | Implemented |
AS0562 # 02 Y:2023 | 02 | 2023 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $4,196 | $37 | Implemented |
AS0562 # 03 Y:2023 | 03 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,428 | $1,545 | Implemented |
AS0562 # 05 Y:2023 | 05 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $301 | $56 | Implemented |
AS0562 # 01 Y:2023 | 01 | 2023 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $20,350 | $500 | Implemented |
MU0032 # 01 Y:2023 | 01 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $465 | $0 | Implemented |
MU0032 # 03 Y:2023 | 03 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $36 | $126 | Implemented |
LS2308 # 03 Y:2023 | 03 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $878 | $525 | Implemented |
AS0552 # 06 Y:2023 | 06 | 2023 | SHADE WINDOWS FROM SUMMER SUN | $281 | $550 | Implemented |
AS0552 # 05 Y:2023 | 05 | 2023 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $357 | $10,234 | Implemented |
AS0552 # 02 Y:2023 | 02 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,547 | $1,915 | Implemented |
OR0770 # 03 Y:2023 | 03 | 2023 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $4,249 | $9,000 | Implemented |
OR0770 # 01 Y:2023 | 01 | 2023 | PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT | $2,142 | $6,704 | Implemented |
DL0223 # 01 Y:2023 | 01 | 2023 | ELIMINATE/REDUCE AN OPERATION | $9,025 | $0 | Implemented |
DL0223 # 04 Y:2023 | 04 | 2023 | INSTALL ADEQUATE DRYERS ON AIR LINES TO ELIMINATE BLOWDOWN | $994 | $4,800 | Implemented |
DL0223 # 02 Y:2023 | 02 | 2023 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $1,437 | $1,030 | Implemented |
SF0598 # 07 Y:2023 | 07 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,843 | $8,505 | Implemented |
SF0598 # 05 Y:2023 | 05 | 2023 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $5,883 | $23,100 | Implemented |
SF0598 # 01 Y:2023 | 01 | 2023 | USE HIGHEST TEMPERATURE FOR CHILLING OR COLD STORAGE | $10,131 | $0 | Implemented |
SF0598 # 02 Y:2023 | 02 | 2023 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $3,805 | $1,551 | Implemented |
DL0219 # 06 Y:2023 | 06 | 2023 | REPLACE HEAT TREATING OVEN WITH MORE EFFICIENT UNIT | $11,196 | $50,000 | Implemented |
DL0219 # 05 Y:2023 | 05 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $6,974 | $10,600 | Implemented |
DL0219 # 01 Y:2023 | 01 | 2023 | AIR CONDITION ONLY SPACE NECESSARY | $496 | $0 | Implemented |