Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
3,422
matching recommendationsSIC | 208 | Beverages |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SU0570 # 05 Y:2025 | 05 | 2025 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $1,569 | $2,693 | n/a |
SU0570 # 04 Y:2025 | 04 | 2025 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,489 | $3,432 | n/a |
SU0570 # 03 Y:2025 | 03 | 2025 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $3,146 | $1,150 | n/a |
SU0570 # 02 Y:2025 | 02 | 2025 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $6,574 | $1,490 | n/a |
SU0570 # 01 Y:2025 | 01 | 2025 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $30,496 | $65 | n/a |
SF0633 # 01 Y:2025 | 01 | 2025 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $28,680 | $0 | n/a |
SF0633 # 02 Y:2025 | 02 | 2025 | TURN OFF EQUIPMENT WHEN NOT IN USE | $3,867 | $0 | n/a |
SF0633 # 03 Y:2025 | 03 | 2025 | REPAIR AND ELIMINATE STEAM LEAKS | $2,640 | $0 | n/a |
SF0633 # 04 Y:2025 | 04 | 2025 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $12,083 | $2,208 | n/a |
SF0633 # 05 Y:2025 | 05 | 2025 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $32,787 | $17,210 | n/a |
SF0633 # 06 Y:2025 | 06 | 2025 | INSULATE BARE EQUIPMENT | $3,235 | $4,152 | n/a |
SF0633 # 07 Y:2025 | 07 | 2025 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $10,943 | $20,376 | n/a |
SF0633 # 08 Y:2025 | 08 | 2025 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $32,940 | $114,566 | n/a |
SF0633 # 09 Y:2025 | 09 | 2025 | MINIMIZE WATER USAGE | $3,105 | $23,556 | n/a |
SF0633 # 10 Y:2025 | 10 | 2025 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $8,335 | $80,990 | n/a |
SF0633 # 11 Y:2025 | 11 | 2025 | USE SOLAR HEAT TO MAKE ELECTRICTY | $223,918 | $872,791 | n/a |
AS0601 # 07 Y:2025 | 07 | 2025 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $105 | $180 | n/a |
AS0601 # 06 Y:2025 | 06 | 2025 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $416 | $942 | n/a |
AS0601 # 05 Y:2025 | 05 | 2025 | INSULATE BARE EQUIPMENT | $852 | $3,546 | n/a |
AS0601 # 04 Y:2025 | 04 | 2025 | USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE | $4,347 | $618 | n/a |
AS0601 # 03 Y:2025 | 03 | 2025 | USE SOLAR HEAT TO MAKE ELECTRICTY | $21,962 | $176,288 | n/a |
AS0601 # 02 Y:2025 | 02 | 2025 | RECOVER AND REUSE WASTE MATERIAL | $76,561 | $120,000 | n/a |
AS0601 # 01 Y:2025 | 01 | 2025 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $130,000 | $66,000 | n/a |
SF0631 # 01 Y:2025 | 01 | 2025 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $17,844 | $0 | n/a |
SF0631 # 02 Y:2025 | 02 | 2025 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $16,164 | $441 | n/a |