Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
3,342
matching recommendationsSIC | 208 | Beverages |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UU0115 # 01 Y:2017 | 01 | 2017 | DISCONNECT BALLASTS | $296 | $0 | Implemented |
UU0115 # 02 Y:2017 | 02 | 2017 | INSTALL OCCUPANCY SENSORS | $444 | $438 | Implemented |
UU0115 # 03 Y:2017 | 03 | 2017 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,840 | $0 | Implemented |
UU0115 # 04 Y:2017 | 04 | 2017 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $931 | $2,500 | Not Implemented |
UU0115 # 05 Y:2017 | 05 | 2017 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $8,766 | $0 | Implemented |
AM0723 # 01 Y:2017 | 01 | 2017 | OPTIMIZE PLANT POWER FACTOR | $12,900 | $23,700 | Implemented |
AM0723 # 02 Y:2017 | 02 | 2017 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $12,700 | $0 | Not Implemented |
AM0723 # 03 Y:2017 | 03 | 2017 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $8,600 | $340 | Implemented |
AM0723 # 04 Y:2017 | 04 | 2017 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,230 | $2,500 | Implemented |
AM0723 # 05 Y:2017 | 05 | 2017 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $10,380 | $3,000 | Implemented |
AM0723 # 06 Y:2017 | 06 | 2017 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,260 | $3,480 | Not Implemented |
AM0723 # 07 Y:2017 | 07 | 2017 | USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL | $3,200 | $0 | Implemented |
AM0723 # 08 Y:2017 | 08 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,230 | $4,350 | Implemented |
AM0723 # 09 Y:2017 | 09 | 2017 | USE SYNTHETIC LUBRICANT | $860 | $0 | Not Implemented |
AM0723 # 10 Y:2017 | 10 | 2017 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $580 | $980 | Not Implemented |
OR0682 # 01 Y:2017 | 01 | 2017 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $104,297 | $70,000 | Not Implemented |
OR0682 # 02 Y:2017 | 02 | 2017 | REPLACE BOILER | $4,289 | $23,625 | Not Implemented |
OR0682 # 03 Y:2017 | 03 | 2017 | REPLACE BOILER | $1,937 | $9,815 | Not Implemented |
SF0494 # 01 Y:2016 | 01 | 2016 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $2,238 | $0 | Implemented |
SF0494 # 02 Y:2016 | 02 | 2016 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $270 | $0 | Implemented |
SF0494 # 03 Y:2016 | 03 | 2016 | INSTALL / REPAIR INSULATION ON STEAM LINES | $5,772 | $2,510 | Implemented |
SF0494 # 04 Y:2016 | 04 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,469 | $4,948 | Implemented |
SF0494 # 05 Y:2016 | 05 | 2016 | MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE | $1,493 | $5,050 | Not Implemented |
SF0494 # 06 Y:2016 | 06 | 2016 | INSTALL OCCUPANCY SENSORS | $567 | $2,381 | Implemented |
SF0494 # 07 Y:2016 | 07 | 2016 | USE SOLAR HEAT TO MAKE ELECTRICTY | $50,748 | $406,834 | Implemented |