Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
83
matching recommendationsSIC | 208 | Beverages |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UU0034 # 01 Y:2002 | 01 | 2002 | OPTIMIZE PLANT POWER FACTOR | $3,790 | $2,000 | Not Implemented |
UU0034 # 04 Y:2002 | 04 | 2002 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $10,560 | $0 | Not Implemented |
UU0034 # 05 Y:2002 | 05 | 2002 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,759 | $800 | Not Implemented |
UU0034 # 03 Y:2002 | 03 | 2002 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,938 | $1,000 | Not Implemented |
UU0034 # 02 Y:2002 | 02 | 2002 | INSTALL / REPAIR INSULATION ON STEAM LINES | $2,627 | $3,621 | Not Implemented |
AS0331 # 09 Y:2002 | 09 | 2002 | PAY BILLS ON TIME TO AVOID LATE FEES | $819 | $144 | Implemented |
AS0331 # 05 Y:2002 | 05 | 2002 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $498 | $542 | Implemented |
AS0331 # 04 Y:2002 | 04 | 2002 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $34,077 | $400 | Not Implemented |
AS0331 # 03 Y:2002 | 03 | 2002 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $13,966 | $20 | Implemented |
AS0331 # 02 Y:2002 | 02 | 2002 | INSTALL SKYLIGHTS | $17,275 | $26,928 | Not Implemented |
AS0331 # 01 Y:2002 | 01 | 2002 | TURN OFF EQUIPMENT WHEN NOT IN USE | $4,752 | $3,880 | Not Implemented |
AS0331 # 06 Y:2002 | 06 | 2002 | INSTALL / REPAIR INSULATION ON STEAM LINES | $371 | $63 | Implemented |
AS0331 # 07 Y:2002 | 07 | 2002 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $398 | $0 | Not Implemented |
AS0331 # 08 Y:2002 | 08 | 2002 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $89,018 | $19,710 | Implemented |
UF0301 # 08 Y:2002 | 08 | 2002 | PURCHASE EQUIPMENT INSTEAD OF LEASING | $70,176 | $0 | Not Implemented |
UF0301 # 02 Y:2002 | 02 | 2002 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $1,352 | $134 | Not Implemented |
UF0301 # 01 Y:2002 | 01 | 2002 | TURN OFF EQUIPMENT WHEN NOT IN USE | $1,016 | $0 | Not Implemented |
UF0301 # 07 Y:2002 | 07 | 2002 | RECOVER AND REUSE WASTE MATERIAL | $40,494 | $1,035 | Not Implemented |
UF0301 # 06 Y:2002 | 06 | 2002 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $16,517 | $16,521 | Not Implemented |
UF0301 # 05 Y:2002 | 05 | 2002 | USE HEAT IN FLUE GASES TO PREHEAT PRODUCTS OR MATERIALS | $51,092 | $121,957 | Not Implemented |
UF0301 # 04 Y:2002 | 04 | 2002 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,526 | $1,768 | Not Implemented |
UF0301 # 03 Y:2002 | 03 | 2002 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $809 | $0 | Not Implemented |
UF0301 # 09 Y:2002 | 09 | 2002 | ELIMINATE/REDUCE REDUNDANT INSPECTIONS | $56,304 | $376 | Not Implemented |
OR0410 # 01 Y:2002 | 01 | 2002 | MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE | $17,362 | $0 | Not Implemented |
OR0410 # 03 Y:2002 | 03 | 2002 | UPGRADE CONTROLS ON COMPRESSORS | $3,700 | $2,000 | Not Implemented |