IAC Assessment: OR0410
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: OR0410
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Oregon State University
Assessment Year 2002
Principal Product Hops extract
NAICS n/a
SIC 2087 - Flavoring Extracts And Syrups, Nec
Sales $10,000,000-$50,000,000
# of Employees 40
Plant Area (Sq.Ft.) 0
Annual Production 1,170,000 Pounds
Production Hrs. Annual 6,000
Location (State) WA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $175,339 5,138,560 kWh $0.03
Electricity Demand $40,514 12,204 kW-months/year $3.32
TOTAL ENERGY COSTS $215,853
RECOMMENDED SAVINGS* $32,626 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $11,265
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Electricity Usage Electricity Demand
$ kWh $ kW-months/year
01: 2.2621 MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE Savings:
$17,362
Cost:
-
$17,362 515,638 - - $17,362
515,638
kWh
-
-
kW-months/year
02: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS Savings:
$8,208
Cost:
$22,848
$6,559 196,504 $1,649 497 $6,559
196,504
kWh
$1,649
497
kW-months/year
03: 2.4224 UPGRADE CONTROLS ON COMPRESSORS Savings:
$3,700
Cost:
$2,000
$3,186 95,460 $514 155 $3,186
95,460
kWh
$514
155
kW-months/year
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$3,057
Cost:
$4,025
$2,690 80,592 $367 110 $2,690
80,592
kWh
$367
110
kW-months/year
05: 2.7124 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED Savings:
$299
Cost:
$600
$263 7,884 $36 11 $263
7,884
kWh
$36
11
kW-months/year
TOTAL RECOMMENDED Savings:
$32,626
Cost:
$29,473
$30,060 896,078 $2,566 773 $30,060
896,078
kWh
$2,566
773
kW-months/year
TOTAL IMPLEMENTED Savings:
$11,265
Cost:
$26,873
$9,249 277,096 $2,016 607 $9,249
277,096
kWh
$2,016
607
kW-months/year
Savings
Cost
$ kWh $ kW-months/year
Electricity Usage Electricity Demand Electricity Usage Electricity Demand