Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
17
matching recommendationsSIC | 2085 | Distilled And Blended Liquors |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
TT0081 # 02 Y:2011 | 02 | 2011 | USE STEAM PRESSURE REDUCTION TO GENERATE POWER | $204,112 | $553,850 | Not Implemented |
TT0081 # 03 Y:2011 | 03 | 2011 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $18,218 | $44,000 | Not Implemented |
TT0081 # 04 Y:2011 | 04 | 2011 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,662 | $5 | Not Implemented |
TT0081 # 05 Y:2011 | 05 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $58,700 | $103,900 | Implemented |
TT0081 # 06 Y:2011 | 06 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $34,694 | $70,320 | Implemented |
TT0081 # 07 Y:2011 | 07 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,492 | $8,160 | Implemented |
TT0081 # 08 Y:2011 | 08 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,580 | $22,680 | Implemented |
TT0081 # 01 Y:2011 | 01 | 2011 | REDUCE COMBUSTION AIR FLOW TO OPTIMUM | $89,000 | $24,500 | Not Implemented |
UF0446 # 09 Y:2011 | 09 | 2011 | MODERATE COOLING TOWER OUTLET TEMPERATURE | $1,662 | $8,210 | Not Implemented |
UF0446 # 08 Y:2011 | 08 | 2011 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $9,593 | $25,700 | Not Implemented |
UF0446 # 07 Y:2011 | 07 | 2011 | COVER OPEN TANKS | $2,910 | $1,175 | Not Implemented |
UF0446 # 06 Y:2011 | 06 | 2011 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $86,813 | $350,000 | Not Implemented |
UF0446 # 05 Y:2011 | 05 | 2011 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $2,063 | $0 | Not Implemented |
UF0446 # 04 Y:2011 | 04 | 2011 | INSTALL OCCUPANCY SENSORS | $3,392 | $396 | Not Implemented |
UF0446 # 03 Y:2011 | 03 | 2011 | LOWER LIGHT FIXTURES IN HIGH CEILING AREAS | $11,224 | $3,045 | Not Implemented |
UF0446 # 02 Y:2011 | 02 | 2011 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $6,009 | $1,320 | Not Implemented |
UF0446 # 01 Y:2011 | 01 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $20,055 | $43,715 | Not Implemented |