Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,757
matching recommendationsSIC | 2086 | Bottled And Canned Soft Drinks |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
CO0249 # 07 Y:1992 | 07 | 1992 | CLOSE HOLES AND OPENINGS IN BUILDING SUCH AS BROKEN WINDOWS | $2,590 | $3,000 | Not Implemented |
CO0249 # 08 Y:1992 | 08 | 1992 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $2,390 | $6,430 | Not Implemented |
TN0456 # 01 Y:1992 | 01 | 1992 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $1,838 | $3,300 | Not Implemented |
TN0456 # 02 Y:1992 | 02 | 1992 | IMPROVE LUBRICATION PRACTICES | $2,396 | $0 | Not Implemented |
TN0456 # 03 Y:1992 | 03 | 1992 | INSTALL / REPAIR INSULATION ON CONDENSATE LINES | $610 | $45 | Not Implemented |
TN0456 # 04 Y:1992 | 04 | 1992 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,806 | $470 | Not Implemented |
TN0456 # 05 Y:1992 | 05 | 1992 | INSTALL TIMERS AND/OR THERMOSTATS | $787 | $420 | Not Implemented |
TN0456 # 06 Y:1992 | 06 | 1992 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $786 | $700 | Not Implemented |
CO0238 # 01 Y:1992 | 01 | 1992 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $700 | $250 | Implemented |
CO0238 # 02 Y:1992 | 02 | 1992 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $250 | $220 | Implemented |
CO0238 # 03 Y:1992 | 03 | 1992 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $300 | $450 | Implemented |
CO0238 # 04 Y:1992 | 04 | 1992 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,540 | $820 | Implemented |
CO0238 # 05 Y:1992 | 05 | 1992 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $540 | $200 | Implemented |
CO0238 # 06 Y:1992 | 06 | 1992 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $320 | $1,000 | Implemented |
CO0238 # 07 Y:1992 | 07 | 1992 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $250 | $1,060 | Implemented |
IA0004 # 01 Y:1991 | 01 | 1991 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $559 | $0 | Implemented |
IA0004 # 02 Y:1991 | 02 | 1991 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,401 | $2,453 | Implemented |
IA0004 # 03 Y:1991 | 03 | 1991 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,523 | $1,200 | Implemented |
IA0004 # 04 Y:1991 | 04 | 1991 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $531 | $1,703 | Implemented |
IA0004 # 05 Y:1991 | 05 | 1991 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $654 | $889 | Implemented |
IA0004 # 07 Y:1991 | 07 | 1991 | RECOVER WASTE HEAT FROM EQUIPMENT | $827 | $686 | Implemented |
IA0004 # 08 Y:1991 | 08 | 1991 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $199 | $20 | Implemented |
RU0133 # 01 Y:1991 | 01 | 1991 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $2,491 | $0 | Implemented |
RU0133 # 02 Y:1991 | 02 | 1991 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,929 | $0 | Implemented |
RU0133 # 03 Y:1991 | 03 | 1991 | INSULATE BARE EQUIPMENT | $460 | $166 | Implemented |