Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
3,008
matching recommendationsSIC | 209 | Misc. Food And Kindred Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
TT0114 # 07 Y:2013 | 07 | 2013 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $7,988 | $15,000 | Not Implemented |
IA0495 # 01 Y:2013 | 01 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,154 | $13,790 | Implemented |
IA0495 # 02 Y:2013 | 02 | 2013 | INSTALL OCCUPANCY SENSORS | $189 | $612 | Implemented |
IA0495 # 03 Y:2013 | 03 | 2013 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $1,071 | $741 | Implemented |
IA0495 # 04 Y:2013 | 04 | 2013 | DIRECT WARMEST AIR TO COMBUSTION INTAKE | $623 | $350 | Not Implemented |
IA0495 # 05 Y:2013 | 05 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $853 | $500 | Implemented |
IA0495 # 06 Y:2013 | 06 | 2013 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $106 | $35 | Implemented |
IA0495 # 07 Y:2013 | 07 | 2013 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $2,715 | $11,000 | Implemented |
UD0877 # 01 Y:2013 | 01 | 2013 | ELIMINATE THIRD SHIFT | $75,782 | $0 | Implemented |
UD0877 # 02 Y:2013 | 02 | 2013 | METER WASTE WATER | $18,660 | $1,000 | Implemented |
UD0877 # 03 Y:2013 | 03 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $8,981 | $14,250 | Not Implemented |
UD0877 # 04 Y:2013 | 04 | 2013 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $5,143 | $8,200 | Not Implemented |
UD0877 # 05 Y:2013 | 05 | 2013 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $4,183 | $1,000 | Not Implemented |
UD0877 # 06 Y:2013 | 06 | 2013 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $2,095 | $0 | Implemented |
UD0877 # 07 Y:2013 | 07 | 2013 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $262 | $500 | Not Implemented |
UD0877 # 08 Y:2013 | 08 | 2013 | USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY | $61,182 | $25,000 | Implemented |
UD0877 # 09 Y:2013 | 09 | 2013 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $685 | $2,000 | Implemented |
OR0599 # 01 Y:2012 | 01 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,611 | $12,467 | Implemented |
OR0599 # 02 Y:2012 | 02 | 2012 | INSTALL AUTOMATIC PACKING EQUIPMENT | $35,308 | $0 | Implemented |
OR0599 # 03 Y:2012 | 03 | 2012 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $1,422 | $0 | Not Implemented |
OR0599 # 04 Y:2012 | 04 | 2012 | MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE | $1,409 | $0 | Implemented |
OR0599 # 05 Y:2012 | 05 | 2012 | USE SOLAR HEAT TO MAKE ELECTRICTY | $1,964 | $17,576 | Not Implemented |
BS0010 # 01 Y:2012 | 01 | 2012 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $289 | $630 | Not Implemented |
BS0010 # 02 Y:2012 | 02 | 2012 | INSULATE BARE EQUIPMENT | $222 | $512 | Implemented |
BS0010 # 03 Y:2012 | 03 | 2012 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $6,826 | $750 | Not Implemented |