Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
199
matching recommendationsSIC | 209 | Misc. Food And Kindred Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UF0168 # 09 Y:1997 | 09 | 1997 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $23,400 | $0 | Not Implemented |
UF0139 # 01 Y:1996 | 01 | 1996 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $75,430 | $0 | Implemented |
UF0139 # 02 Y:1996 | 02 | 1996 | PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER | $18,648 | $0 | Implemented |
UF0139 # 03 Y:1996 | 03 | 1996 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,180 | $11,068 | Not Implemented |
UF0139 # 04 Y:1996 | 04 | 1996 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $24,372 | $57,360 | Not Implemented |
UF0139 # 05 Y:1996 | 05 | 1996 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,506 | $350 | Implemented |
UF0139 # 06 Y:1996 | 06 | 1996 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $16,271 | $35,000 | Not Implemented |
UF0139 # 07 Y:1996 | 07 | 1996 | INSTALL OR UPGRADE INSULATION ON HVAC DISTRIBUTION SYSTEMS | $1,581 | $1,125 | Not Implemented |
UF0139 # 08 Y:1996 | 08 | 1996 | RECOVER WASTE HEAT FROM EQUIPMENT | $6,118 | $10,800 | Not Implemented |
UF0139 # 09 Y:1996 | 09 | 1996 | USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL | $7,200 | $0 | Not Implemented |
UF0034 # 01 Y:1992 | 01 | 1992 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $5,358 | $0 | Not Implemented |
UF0034 # 02 Y:1992 | 02 | 1992 | USE PROPERLY DESIGNED AND SIZED HVAC EQUIPMENT | $11,737 | $14,960 | Not Implemented |
UF0034 # 03 Y:1992 | 03 | 1992 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $2,962 | $18,601 | Implemented |
UF0034 # 04 Y:1992 | 04 | 1992 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,299 | $400 | Implemented |
UF0034 # 05 Y:1992 | 05 | 1992 | REDUCE AIR CONDITIONING LOAD BY EVAPORATING WATER FROM ROOF | $51,194 | $68,400 | Not Implemented |
UF0034 # 06 Y:1992 | 06 | 1992 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $3,213 | $1,000 | Implemented |
UF0034 # 07 Y:1992 | 07 | 1992 | RECOVER WASTE HEAT FROM EQUIPMENT | $7,986 | $5,200 | Implemented |
UF0007 # 01 Y:1991 | 01 | 1991 | INSTALL SPECTRAL REFLECTORS / DELAMP | $8,472 | $7,770 | Not Implemented |
UF0007 # 02 Y:1991 | 02 | 1991 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $818 | $1,805 | Not Implemented |
UF0007 # 03 Y:1991 | 03 | 1991 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $4,212 | $0 | Not Implemented |
UF0007 # 04 Y:1991 | 04 | 1991 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,038 | $0 | Not Implemented |
UF0007 # 05 Y:1991 | 05 | 1991 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $928 | $600 | Not Implemented |
UF0007 # 06 Y:1991 | 06 | 1991 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $395 | $2,443 | Not Implemented |
UF0007 # 07 Y:1991 | 07 | 1991 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $56 | $291 | Not Implemented |