Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
238
matching recommendationsSIC | 209 | Misc. Food And Kindred Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
KG0026 # 07 Y:1995 | 07 | 1995 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $494 | $20 | Implemented |
AM0232 # 01 Y:1995 | 01 | 1995 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $397 | $422 | Implemented |
AM0232 # 02 Y:1995 | 02 | 1995 | INSULATE BARE EQUIPMENT | $2,220 | $1,360 | Implemented |
AM0232 # 03 Y:1995 | 03 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,261 | $2,750 | Implemented |
AM0232 # 04 Y:1995 | 04 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $512 | $260 | Implemented |
AM0232 # 05 Y:1995 | 05 | 1995 | USE SYNTHETIC LUBRICANT | $419 | $0 | Implemented |
AM0232 # 06 Y:1995 | 06 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $110 | $248 | Implemented |
KG0009 # 01 Y:1994 | 01 | 1994 | ADJUST BURNERS FOR EFFICIENT OPERATION | $8,262 | $2,500 | Not Implemented |
KG0009 # 02 Y:1994 | 02 | 1994 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $4,500 | $2,500 | Not Implemented |
KG0009 # 03 Y:1994 | 03 | 1994 | TURN OFF EQUIPMENT WHEN NOT IN USE | $3,929 | $0 | Not Implemented |
KG0009 # 04 Y:1994 | 04 | 1994 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $2,984 | $7,370 | Not Implemented |
KG0009 # 05 Y:1994 | 05 | 1994 | RECOVER WASTE HEAT FROM EQUIPMENT | $2,527 | $8,800 | Not Implemented |
KG0009 # 06 Y:1994 | 06 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,017 | $810 | Not Implemented |
KG0009 # 07 Y:1994 | 07 | 1994 | INSTALL TIMERS AND/OR THERMOSTATS | $1,662 | $300 | Not Implemented |
KG0009 # 08 Y:1994 | 08 | 1994 | DIRECT WARMEST AIR TO COMBUSTION INTAKE | $1,387 | $100 | Not Implemented |
KG0009 # 09 Y:1994 | 09 | 1994 | INSTALL OCCUPANCY SENSORS | $371 | $260 | Not Implemented |
KG0006 # 01 Y:1994 | 01 | 1994 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $66,725 | $1,260 | Not Implemented |
KG0006 # 02 Y:1994 | 02 | 1994 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $4,688 | $9,480 | Implemented |
KG0006 # 03 Y:1994 | 03 | 1994 | INSTALL TIMERS AND/OR THERMOSTATS | $3,500 | $1,350 | Not Implemented |
KG0006 # 04 Y:1994 | 04 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,449 | $730 | Implemented |
KG0006 # 05 Y:1994 | 05 | 1994 | INSULATE BARE EQUIPMENT | $1,458 | $270 | Implemented |
KG0006 # 06 Y:1994 | 06 | 1994 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,036 | $3,700 | Not Implemented |
KG0006 # 07 Y:1994 | 07 | 1994 | INSULATE BARE EQUIPMENT | $972 | $188 | Implemented |
AM0145 # 01 Y:1992 | 01 | 1992 | USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY | $11,180 | $7,575 | Implemented |
AM0145 # 02 Y:1992 | 02 | 1992 | USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY | $1,000 | $4,000 | Implemented |