Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
69
matching recommendationsSIC | 22 | Textile Mill Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AM0583 # 06 Y:2010 | 06 | 2010 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $210 | $10 | Implemented |
AM0583 # 04 Y:2010 | 04 | 2010 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,120 | $500 | Implemented |
AM0583 # 01 Y:2010 | 01 | 2010 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $12,970 | $26,490 | Implemented |
AM0583 # 07 Y:2010 | 07 | 2010 | USE SYNTHETIC LUBRICANT | $130 | $0 | Implemented |
AM0583 # 05 Y:2010 | 05 | 2010 | PAY UTILITY BILLS ON TIME | $479 | $0 | Implemented |
AM0583 # 03 Y:2010 | 03 | 2010 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,447 | $680 | Implemented |
AM0583 # 02 Y:2010 | 02 | 2010 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $7,360 | $0 | Implemented |
TA0056 # 05 Y:2003 | 05 | 2003 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $770 | $0 | Implemented |
TA0056 # 03 Y:2003 | 03 | 2003 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $6,726 | $0 | Implemented |
TA0056 # 02 Y:2003 | 02 | 2003 | OPTIMIZE PRODUCTION LOT SIZES AND INVENTORIES | $13,500 | $1,075 | Not Implemented |
TA0056 # 04 Y:2003 | 04 | 2003 | INSTALL TIMERS AND/OR THERMOSTATS | $880 | $325 | Implemented |
TA0056 # 01 Y:2003 | 01 | 2003 | RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE HANDLING COSTS | $190,000 | $141,875 | Not Implemented |
TA0056 # 06 Y:2003 | 06 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $710 | $1,128 | Implemented |
AM0434 # 10 Y:2003 | 10 | 2003 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $965 | $800 | Implemented |
AM0434 # 01 Y:2003 | 01 | 2003 | REPLACE OLD MACHINE WITH NEW AUTOMATIC MULTI-STATION TOOL | $122,000 | $2,050,000 | n/a |
AM0434 # 02 Y:2003 | 02 | 2003 | PAY BILLS ON TIME TO AVOID LATE FEES | $15,830 | $0 | Implemented |
AM0434 # 03 Y:2003 | 03 | 2003 | REGRIND, REUSE, OR SELL SCRAP PLASTIC PARTS | $8,000 | $800 | Implemented |
AM0434 # 04 Y:2003 | 04 | 2003 | PURCHASE NEW EQUIPMENT TO REDUCE MATERIAL USE / COST | $7,300 | $89,640 | Implemented |
AM0434 # 05 Y:2003 | 05 | 2003 | USE SYNTHETIC LUBRICANT | $4,520 | $0 | Not Implemented |
AM0434 # 06 Y:2003 | 06 | 2003 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $3,510 | $0 | Implemented |
AM0434 # 07 Y:2003 | 07 | 2003 | ELIMINATE PRACTICE OF MIXING WASTE STREAMS | $3,500 | $0 | Implemented |
AM0434 # 08 Y:2003 | 08 | 2003 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $2,300 | $0 | Implemented |
AM0434 # 09 Y:2003 | 09 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,670 | $1,440 | Not Implemented |
AM0329 # 01 Y:1998 | 01 | 1998 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,000 | $500 | Implemented |
AM0329 # 06 Y:1998 | 06 | 1998 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $393 | $392 | Implemented |