Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
34
matching recommendationsSIC | 227 | Carpets And Rugs |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
GT0598 # 07 Y:1996 | 07 | 1996 | INCREASE AMOUNT OF CONDENSATE RETURNED | $124,000 | $187,500 | Not Implemented |
GT0598 # 05 Y:1996 | 05 | 1996 | PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER | $219,570 | $122,000 | Not Implemented |
GT0598 # 03 Y:1996 | 03 | 1996 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,350 | $2,210 | Implemented |
GT0598 # 08 Y:1996 | 08 | 1996 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $212,520 | $600,000 | Not Implemented |
GT0598 # 06 Y:1996 | 06 | 1996 | UPGRADE CONTROLS ON COMPRESSORS | $4,500 | $7,000 | Not Implemented |
GT0598 # 02 Y:1996 | 02 | 1996 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $29,210 | $151,530 | Not Implemented |
GT0598 # 01 Y:1996 | 01 | 1996 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $3,850 | $38,240 | Implemented |
GT0598 # 04 Y:1996 | 04 | 1996 | ENHANCE SENSITIVITY OF TEMPERATURE CONTROL AND CUTOFF | $51,750 | $6,000 | Not Implemented |
GT0595 # 08 Y:1996 | 08 | 1996 | MINIMIZE WATER USAGE | $56,000 | $18,000 | Not Implemented |
GT0595 # 07 Y:1996 | 07 | 1996 | PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER | $152,800 | $102,000 | Not Implemented |
GT0595 # 06 Y:1996 | 06 | 1996 | USE MINIMUM STEAM OPERATING PRESSURE | $124,000 | $27,000 | Not Implemented |
GT0595 # 05 Y:1996 | 05 | 1996 | USE PHOTOCELL CONTROLS | $163 | $109 | Not Implemented |
GT0595 # 04 Y:1996 | 04 | 1996 | INSTALL AUTOMATIC STACK DAMPER | $48,900 | $75,450 | Not Implemented |
GT0595 # 03 Y:1996 | 03 | 1996 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $5,220 | $8,520 | Not Implemented |
GT0595 # 02 Y:1996 | 02 | 1996 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,611 | $25,662 | Not Implemented |
GT0595 # 01 Y:1996 | 01 | 1996 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,587 | $17,013 | Implemented |
GT0584 # 09 Y:1996 | 09 | 1996 | KEEP BOILER TUBES CLEAN | $8,890 | $0 | Not Implemented |
GT0584 # 10 Y:1996 | 10 | 1996 | ELIMINATE/REDUCE AN OPERATION | $123,180 | $600,000 | Not Implemented |
GT0584 # 08 Y:1996 | 08 | 1996 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $1,150 | $0 | Implemented |
GT0584 # 07 Y:1996 | 07 | 1996 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $11,300 | $0 | Implemented |
GT0584 # 06 Y:1996 | 06 | 1996 | PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER | $52,000 | $0 | Implemented |
GT0584 # 05 Y:1996 | 05 | 1996 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $12,600 | $0 | Not Implemented |
GT0584 # 04 Y:1996 | 04 | 1996 | UPGRADE CONTROLS ON COMPRESSORS | $34,600 | $7,000 | Not Implemented |
GT0584 # 03 Y:1996 | 03 | 1996 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,430 | $350 | Implemented |
GT0584 # 02 Y:1996 | 02 | 1996 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,510 | $22,150 | Implemented |