Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
41
matching recommendationsSIC | 2273 | Carpets And Rugs |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
GT0626 # 08 Y:1997 | 08 | 1997 | USE A DIFFERENT OR RECYCLED RAW MATERIAL | $1,315 | $438 | Not Implemented |
GT0626 # 07 Y:1997 | 07 | 1997 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $26,666 | $4,200 | Implemented |
GT0626 # 06 Y:1997 | 06 | 1997 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $2,570 | $7,580 | Not Implemented |
GT0626 # 05 Y:1997 | 05 | 1997 | INSTALL / REPAIR INSULATION ON STEAM LINES | $400 | $620 | Implemented |
GT0626 # 04 Y:1997 | 04 | 1997 | REPLACE CITY WATER WITH RECYCLED WATER VIA COOLING TOWER | $2,730 | $1,420 | Not Implemented |
GT0626 # 03 Y:1997 | 03 | 1997 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,580 | $11,230 | Not Implemented |
GT0626 # 02 Y:1997 | 02 | 1997 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $21,185 | $0 | Implemented |
GT0626 # 01 Y:1997 | 01 | 1997 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,741 | $950 | Implemented |
GT0622 # 08 Y:1997 | 08 | 1997 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $207,108 | $330,000 | Not Implemented |
GT0622 # 01 Y:1997 | 01 | 1997 | INSTALL / REPAIR INSULATION ON STEAM LINES | $980 | $2,000 | Implemented |
GT0622 # 02 Y:1997 | 02 | 1997 | REPAIR AND ELIMINATE STEAM LEAKS | $3,470 | $1,200 | Implemented |
GT0622 # 03 Y:1997 | 03 | 1997 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $94 | $240 | Not Implemented |
GT0622 # 04 Y:1997 | 04 | 1997 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,626 | $300 | Implemented |
GT0622 # 05 Y:1997 | 05 | 1997 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $1,060 | $632 | Implemented |
GT0622 # 06 Y:1997 | 06 | 1997 | MINIMIZE WATER USAGE | $533 | $0 | Not Implemented |
GT0622 # 07 Y:1997 | 07 | 1997 | USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION | $4,999 | $3,200 | Not Implemented |
GT0622 # 09 Y:1997 | 09 | 1997 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $6,890 | $0 | Not Implemented |
GT0614 # 07 Y:1997 | 07 | 1997 | USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION | $6,643 | $4,500 | Implemented |
GT0614 # 10 Y:1997 | 10 | 1997 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $365,300 | $800,000 | Not Implemented |
GT0614 # 09 Y:1997 | 09 | 1997 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $10,701 | $5,100 | Not Implemented |
GT0614 # 08 Y:1997 | 08 | 1997 | ENHANCE SENSITIVITY OF TEMPERATURE CONTROL AND CUTOFF | $23,450 | $300 | Not Implemented |
GT0614 # 06 Y:1997 | 06 | 1997 | USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION | $94,300 | $40,000 | Not Implemented |
GT0614 # 05 Y:1997 | 05 | 1997 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $365,536 | $238,000 | Not Implemented |
GT0614 # 04 Y:1997 | 04 | 1997 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $18,883 | $12,000 | Not Implemented |
GT0614 # 03 Y:1997 | 03 | 1997 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $10,030 | $17,130 | Not Implemented |