Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
59
matching recommendationsSIC | 23 | Apparel And Other Textile Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
GT0153 # 01 Y:1982 | 01 | 1982 | INSTALL TIMERS AND/OR THERMOSTATS | $4,196 | $903 | Not Implemented |
GT0153 # 02 Y:1982 | 02 | 1982 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,545 | $625 | Not Implemented |
GT0153 # 03 Y:1982 | 03 | 1982 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $2,945 | $9,000 | Not Implemented |
GT0153 # 04 Y:1982 | 04 | 1982 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $6,549 | $0 | Not Implemented |
GT0153 # 05 Y:1982 | 05 | 1982 | ESTABLISH EQUIPMENT MAINTENANCE SCHEDULE | $1,865 | $1,860 | Not Implemented |
KU0067 # 06 Y:1982 | 06 | 1982 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $420 | $400 | Not Implemented |
TN0140 # 03 Y:1982 | 03 | 1982 | MAINTAIN AIR FILTERS BY CLEANING OR REPLACEMENT | $185 | $0 | Not Implemented |
KU0067 # 05 Y:1982 | 05 | 1982 | INSULATE BARE EQUIPMENT | $675 | $100 | Not Implemented |
KU0067 # 04 Y:1982 | 04 | 1982 | OPTIMIZE PLANT POWER FACTOR | $1,623 | $2,350 | Not Implemented |
KU0067 # 03 Y:1982 | 03 | 1982 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $973 | $139 | Implemented |
KU0067 # 02 Y:1982 | 02 | 1982 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $6,254 | $0 | Implemented |
KU0067 # 01 Y:1982 | 01 | 1982 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,109 | $4,780 | Not Implemented |
UD0047 # 02 Y:1982 | 02 | 1982 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,175 | $122 | Not Implemented |
TN0142 # 02 Y:1982 | 02 | 1982 | USE OPTIMUM THICKNESS INSULATION | $281 | $176 | Not Implemented |
UD0047 # 01 Y:1982 | 01 | 1982 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $3,843 | $600 | Not Implemented |
TN0140 # 02 Y:1982 | 02 | 1982 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $66 | $48 | Not Implemented |
TN0142 # 01 Y:1982 | 01 | 1982 | USE SEPARATE SWITCHES ON PERIMETER LIGHTING WHICH MAY BE TURNED OFF WHEN NATURAL LIGHT IS AVAILABLE | $253 | $1,850 | Not Implemented |
KU0067 # 07 Y:1982 | 07 | 1982 | INSTALL AUTOMATIC STACK DAMPER | $851 | $1,630 | Not Implemented |
KU0067 # 08 Y:1982 | 08 | 1982 | USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE | $798 | $950 | Not Implemented |
UD0047 # 04 Y:1982 | 04 | 1982 | INSTALL / REPAIR INSULATION ON STEAM LINES | $1,352 | $1,500 | Not Implemented |
KU0067 # 09 Y:1982 | 09 | 1982 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $173 | $31 | Implemented |
TN0140 # 01 Y:1982 | 01 | 1982 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $242 | $200 | Not Implemented |
TN0142 # 03 Y:1982 | 03 | 1982 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $472 | $500 | Not Implemented |
UD0047 # 03 Y:1982 | 03 | 1982 | INSTALL / REPAIR INSULATION ON STEAM LINES | $4,878 | $2,288 | Not Implemented |
UD0047 # 05 Y:1982 | 05 | 1982 | INSTALL STORM WINDOWS AND DOORS | $5,066 | $6,048 | Not Implemented |