Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
165
matching recommendationsSIC | 2329 | Men's and Boys' Clothing, Not Elsewhere Classified |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
DS0123 # 04 Y:1998 | 04 | 1998 | INCREASE AMOUNT OF WASTE RECOVERED FOR RESALE | $13,292 | $400 | Not Implemented |
DS0123 # 05 Y:1998 | 05 | 1998 | ESTABLISH EQUIPMENT MAINTENANCE SCHEDULE | $564 | $0 | Implemented |
MS0101 # 08 Y:1998 | 08 | 1998 | COMBINE UTILITY METERS | $420 | $1,225 | Implemented |
MS0101 # 07 Y:1998 | 07 | 1998 | PAY BILLS ON TIME TO AVOID LATE FEES | $207 | $0 | Implemented |
MS0101 # 06 Y:1998 | 06 | 1998 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $7,360 | $420 | Implemented |
MS0101 # 05 Y:1998 | 05 | 1998 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $2,012 | $816 | Not Implemented |
MS0101 # 04 Y:1998 | 04 | 1998 | LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER | $2,750 | $0 | Implemented |
MS0101 # 01 Y:1998 | 01 | 1998 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $1,713 | $5,100 | Not Implemented |
MS0101 # 02 Y:1998 | 02 | 1998 | PREHEAT COMBUSTION AIR WITH WASTE HEAT | $1,593 | $4,400 | Not Implemented |
MS0101 # 03 Y:1998 | 03 | 1998 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,386 | $1,000 | Implemented |
MS0056 # 01 Y:1996 | 01 | 1996 | AVOID INTRODUCING HOT, HUMID, OR DIRTY AIR INTO HVAC SYSTEM | $2,295 | $3,000 | Implemented |
MS0056 # 02 Y:1996 | 02 | 1996 | INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS | $9,787 | $24,862 | Implemented |
MS0056 # 03 Y:1996 | 03 | 1996 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $887 | $1,000 | Implemented |
MS0056 # 04 Y:1996 | 04 | 1996 | USE RE-USABLE FILTERS | $1,090 | $900 | Not Implemented |
MS0056 # 05 Y:1996 | 05 | 1996 | INCREASE AMOUNT OF WASTE RECOVERED FOR RESALE | $2,940 | $0 | Not Implemented |
AR0073 # 02 Y:1995 | 02 | 1995 | OPTIMIZE PLANT POWER FACTOR | $2,641 | $4,320 | Not Implemented |
AR0073 # 03 Y:1995 | 03 | 1995 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,124 | $300 | Implemented |
AR0073 # 04 Y:1995 | 04 | 1995 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,644 | $150 | Implemented |
AR0073 # 05 Y:1995 | 05 | 1995 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $6,229 | $5,120 | Implemented |
AR0073 # 06 Y:1995 | 06 | 1995 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $90,655 | $8,400 | Not Implemented |
AR0073 # 07 Y:1995 | 07 | 1995 | DIRECT WARMEST AIR TO COMBUSTION INTAKE | $515 | $600 | Not Implemented |
AR0073 # 08 Y:1995 | 08 | 1995 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $515 | $1,000 | Implemented |
AR0073 # 09 Y:1995 | 09 | 1995 | MINIMIZE WATER USAGE | $175 | $200 | Implemented |
AR0073 # 01 Y:1995 | 01 | 1995 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $6,271 | $3,600 | Implemented |
NC0042 # 05 Y:1994 | 05 | 1994 | RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR | $505 | $825 | Not Implemented |