Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
7,223
matching recommendationsSIC | 24 | Lumber And Wood Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
GT0494 # 10 Y:1993 | 10 | 1993 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $2,824 | $0 | Not Implemented |
AM0181 # 01 Y:1993 | 01 | 1993 | OPTIMIZE PLANT POWER FACTOR | $3,000 | $6,000 | Implemented |
AM0181 # 02 Y:1993 | 02 | 1993 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,210 | $9,440 | Implemented |
AM0181 # 03 Y:1993 | 03 | 1993 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $1,042 | $2,250 | Not Implemented |
AM0181 # 04 Y:1993 | 04 | 1993 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $820 | $420 | Implemented |
AR0001 # 01 Y:1993 | 01 | 1993 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $5,172 | $200 | Implemented |
AR0001 # 02 Y:1993 | 02 | 1993 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $13,336 | $620 | Implemented |
AR0001 # 03 Y:1993 | 03 | 1993 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $14,158 | $21,800 | Implemented |
AR0001 # 04 Y:1993 | 04 | 1993 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $680 | $70 | Implemented |
AR0001 # 05 Y:1993 | 05 | 1993 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $11,028 | $3,400 | Not Implemented |
AR0001 # 06 Y:1993 | 06 | 1993 | USE STEAM PRESSURE REDUCTION TO GENERATE POWER | $33,492 | $25,300 | Implemented |
AR0001 # 07 Y:1993 | 07 | 1993 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,591 | $227 | Implemented |
OR0173 # 01 Y:1993 | 01 | 1993 | KEEP BOILER TUBES CLEAN | $6,498 | $1,000 | Not Implemented |
OR0173 # 02 Y:1993 | 02 | 1993 | OPTIMIZE PLANT POWER FACTOR | $4,670 | $4,500 | Not Implemented |
OR0173 # 03 Y:1993 | 03 | 1993 | TURN OFF EQUIPMENT WHEN NOT IN USE | $612 | $1,230 | Not Implemented |
OR0173 # 04 Y:1993 | 04 | 1993 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,897 | $5,062 | Not Implemented |
OR0173 # 05 Y:1993 | 05 | 1993 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $370 | $1,036 | Not Implemented |
OR0173 # 06 Y:1993 | 06 | 1993 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $354 | $1,000 | Not Implemented |
OR0173 # 07 Y:1993 | 07 | 1993 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,092 | $3,525 | Not Implemented |
OR0173 # 08 Y:1993 | 08 | 1993 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $9,338 | $41,360 | Not Implemented |
SD0051 # 01 Y:1993 | 01 | 1993 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,002 | $1,890 | Implemented |
SD0051 # 02 Y:1993 | 02 | 1993 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,549 | $3,320 | Implemented |
SD0051 # 03 Y:1993 | 03 | 1993 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $223 | $20 | Not Implemented |
SD0051 # 04 Y:1993 | 04 | 1993 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $544 | $80 | Not Implemented |
SD0051 # 05 Y:1993 | 05 | 1993 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $102 | $0 | Implemented |