Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
17
matching recommendationsSIC | 245 | Wood Buildings And Mobile Homes |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
BS0090 # 01 Y:2016 | 01 | 2016 | TURN OFF EQUIPMENT WHEN NOT IN USE | $2,027 | $1,820 | Implemented |
BS0090 # 02 Y:2016 | 02 | 2016 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,391 | $2,653 | Implemented |
BS0090 # 04 Y:2016 | 04 | 2016 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $942 | $1,373 | Implemented |
BS0090 # 05 Y:2016 | 05 | 2016 | INSTALL OCCUPANCY SENSORS | $395 | $254 | Implemented |
BS0082 # 02 Y:2016 | 02 | 2016 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,517 | $2,325 | Implemented |
BS0082 # 03 Y:2016 | 03 | 2016 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $146 | $300 | Implemented |
BS0082 # 05 Y:2016 | 05 | 2016 | REDESIGN PROCESS | $1,906 | $1,953 | Implemented |
BS0082 # 01 Y:2016 | 01 | 2016 | UPGRADE CONTROLS ON COMPRESSORS | $1,327 | $3,476 | Implemented |
BS0067 # 05 Y:2015 | 05 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $470 | $535 | Implemented |
BS0067 # 04 Y:2015 | 04 | 2015 | UPGRADE CONTROLS ON COMPRESSORS | $1,007 | $1,161 | Implemented |
BS0067 # 03 Y:2015 | 03 | 2015 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $473 | $528 | Implemented |
BS0067 # 02 Y:2015 | 02 | 2015 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $762 | $77 | Implemented |
BS0003 # 05 Y:2012 | 05 | 2012 | USE SEPARATE SWITCHES ON PERIMETER LIGHTING WHICH MAY BE TURNED OFF WHEN NATURAL LIGHT IS AVAILABLE | $458 | $600 | Implemented |
BS0003 # 04 Y:2012 | 04 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $831 | $1,497 | Implemented |
BS0003 # 03 Y:2012 | 03 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,856 | $4,997 | Implemented |
BS0003 # 02 Y:2012 | 02 | 2012 | IMPLEMENT A REGULAR MAINTENANCE PROGRAM TO REDUCE EMISSIONS FROM LEAKY VALVES AND PIPE FITTINGS | $1,528 | $300 | Implemented |
BS0003 # 01 Y:2012 | 01 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,118 | $296 | Implemented |