Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
138
matching recommendationsSIC | 2493 | Reconstituted Wood Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OR0062 # 03 Y:1989 | 03 | 1989 | INSTALL / REPAIR INSULATION ON CONDENSATE LINES | $500 | $255 | Implemented |
OR0062 # 04 Y:1989 | 04 | 1989 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,561 | $1,210 | Implemented |
OR0062 # 05 Y:1989 | 05 | 1989 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $518 | $467 | Implemented |
OR0062 # 06 Y:1989 | 06 | 1989 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $227 | $300 | Not Implemented |
OR0062 # 07 Y:1989 | 07 | 1989 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $642 | $1,144 | Implemented |
OR0062 # 08 Y:1989 | 08 | 1989 | OPTIMIZE PLANT POWER FACTOR | $5,423 | $11,400 | Not Implemented |
OR0055 # 01 Y:1989 | 01 | 1989 | INSULATE BARE EQUIPMENT | $1,145 | $443 | Implemented |
OR0055 # 02 Y:1989 | 02 | 1989 | INSULATE BARE EQUIPMENT | $1,169 | $553 | Implemented |
OR0055 # 03 Y:1989 | 03 | 1989 | DIRECT WARMEST AIR TO COMBUSTION INTAKE | $1,773 | $1,200 | Not Implemented |
OR0055 # 04 Y:1989 | 04 | 1989 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $439 | $425 | Implemented |
OR0055 # 05 Y:1989 | 05 | 1989 | RECOVER WASTE HEAT FROM EQUIPMENT | $4,067 | $947 | Implemented |
OR0055 # 06 Y:1989 | 06 | 1989 | OPTIMIZE PLANT POWER FACTOR | $3,950 | $8,400 | Implemented |
OR0055 # 07 Y:1989 | 07 | 1989 | DIRECT WARMEST AIR TO COMBUSTION INTAKE | $333 | $1,000 | Not Implemented |