Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
3,513
matching recommendationsSIC | 25 | Furniture And Fixtures |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
GT0182 # 03 Y:1983 | 03 | 1983 | ISOLATE HOT OR COLD EQUIPMENT | $2,780 | $1,520 | Not Implemented |
GT0182 # 04 Y:1983 | 04 | 1983 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $2,200 | $7,000 | Not Implemented |
GT0182 # 05 Y:1983 | 05 | 1983 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,230 | $8,940 | Not Implemented |
OK0075 # 01 Y:1983 | 01 | 1983 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $761 | $1,674 | Not Implemented |
OK0075 # 02 Y:1983 | 02 | 1983 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $956 | $53 | Implemented |
OK0075 # 03 Y:1983 | 03 | 1983 | INSTALL TIMERS AND/OR THERMOSTATS | $10,279 | $1,135 | Implemented |
OK0075 # 04 Y:1983 | 04 | 1983 | USE ONLY AMOUNT OF AIR NECESSARY TO PREVENT EXPLOSION HAZARD | $2,140 | $2,725 | Not Implemented |
OK0075 # 05 Y:1983 | 05 | 1983 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $733 | $100 | Not Implemented |
TN0167 # 01 Y:1983 | 01 | 1983 | REDUCE VENTILATION AIR | $23,801 | $11,000 | Not Implemented |
TN0167 # 02 Y:1983 | 02 | 1983 | BURN WOOD BY-PRODUCTS FOR HEAT | $250,513 | $1,000,000 | Not Implemented |
TN0167 # 03 Y:1983 | 03 | 1983 | INSTALL OR UPGRADE INSULATION ON HVAC DISTRIBUTION SYSTEMS | $30,929 | $32,300 | Not Implemented |
TN0167 # 04 Y:1983 | 04 | 1983 | REDUCE VENTILATION AIR | $5,074 | $18,612 | Not Implemented |
UD0066 # 01 Y:1982 | 01 | 1982 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $9,419 | $2,525 | Implemented |
UD0066 # 02 Y:1982 | 02 | 1982 | REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED | $147 | $0 | Implemented |
UD0066 # 03 Y:1982 | 03 | 1982 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $769 | $0 | Implemented |
OK0063 # 01 Y:1982 | 01 | 1982 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,442 | $400 | Not Implemented |
OK0063 # 02 Y:1982 | 02 | 1982 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $345 | $156 | Not Implemented |
OK0063 # 03 Y:1982 | 03 | 1982 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $106 | $205 | Implemented |
OK0063 # 04 Y:1982 | 04 | 1982 | CENTRALIZE CONTROL OF EXHAUST FANS TO ENSURE THEIR SHUTDOWN, OR ESTABLISH PROGRAM TO ENSURE MANUAL SHUTDOWN | $972 | $0 | Not Implemented |
OK0063 # 05 Y:1982 | 05 | 1982 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $2,330 | $0 | Not Implemented |
OK0063 # 06 Y:1982 | 06 | 1982 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $140 | $0 | Not Implemented |
TN0149 # 01 Y:1982 | 01 | 1982 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $230 | $0 | Not Implemented |
TN0149 # 02 Y:1982 | 02 | 1982 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,851 | $0 | Not Implemented |
TN0149 # 03 Y:1982 | 03 | 1982 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,508 | $45,000 | Not Implemented |
TN0129 # 01 Y:1982 | 01 | 1982 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $19,550 | $11,600 | Not Implemented |