Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
3,525
matching recommendationsSIC | 25 | Furniture And Fixtures |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
WV0510 # 02 Y:2015 | 02 | 2015 | INSULATE BARE EQUIPMENT | $47,885 | $8,730 | Not Implemented |
WV0510 # 03 Y:2015 | 03 | 2015 | ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM | $15,681 | $1,000 | Implemented |
WV0510 # 04 Y:2015 | 04 | 2015 | INSTALL OCCUPANCY SENSORS | $9,890 | $3,930 | Implemented |
WV0510 # 05 Y:2015 | 05 | 2015 | OPTIMIZE PLANT POWER FACTOR | $9,408 | $24,300 | Not Implemented |
WV0510 # 06 Y:2015 | 06 | 2015 | DEVELOP A REPAIR/REPLACE POLICY | $5,855 | $1,108 | Implemented |
WV0510 # 07 Y:2015 | 07 | 2015 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $5,050 | $0 | Implemented |
WV0510 # 08 Y:2015 | 08 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,904 | $537 | Implemented |
WV0510 # 09 Y:2015 | 09 | 2015 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $3,824 | $2,324 | Not Implemented |
WV0510 # 10 Y:2015 | 10 | 2015 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,881 | $46 | Implemented |
WV0510 # 11 Y:2015 | 11 | 2015 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $2,210 | $7,073 | Not Implemented |
SU0391 # 01 Y:2015 | 01 | 2015 | IMPLEMENT A REGULAR MAINTENANCE PROGRAM TO REDUCE EMISSIONS FROM LEAKY VALVES AND PIPE FITTINGS | $9,598 | $5,243 | Implemented |
SU0391 # 02 Y:2015 | 02 | 2015 | USE PHOTOCELL CONTROLS | $716 | $367 | Implemented |
SU0391 # 03 Y:2015 | 03 | 2015 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,180 | $2,800 | Not Implemented |
SU0391 # 04 Y:2015 | 04 | 2015 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $64,843 | $97,500 | Not Implemented |
SU0391 # 05 Y:2015 | 05 | 2015 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,806 | $2,683 | Not Implemented |
SU0391 # 06 Y:2015 | 06 | 2015 | INSULATE BARE EQUIPMENT | $938 | $1,414 | Implemented |
SU0391 # 07 Y:2015 | 07 | 2015 | CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES | $584 | $2,876 | Not Implemented |
SU0391 # 08 Y:2015 | 08 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,885 | $9,310 | Not Implemented |
MZ0184 # 01 Y:2015 | 01 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $28,705 | $78,480 | Implemented |
MZ0184 # 02 Y:2015 | 02 | 2015 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $357 | $1,750 | Implemented |
MZ0184 # 03 Y:2015 | 03 | 2015 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $5,611 | $12,500 | Not Implemented |
MZ0184 # 04 Y:2015 | 04 | 2015 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $1,232 | $0 | Implemented |
AM0683 # 01 Y:2015 | 01 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $9,680 | $8,610 | Not Implemented |
AM0683 # 02 Y:2015 | 02 | 2015 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $4,280 | $10 | Implemented |
AM0683 # 03 Y:2015 | 03 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,800 | $1,000 | Implemented |