Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | North Carolina State |
---|---|
Assessment Year | 2016 |
Principal Product | Furniture frames |
NAICS | 337121 - Upholstered Household Furniture Manufacturing |
SIC | 2512 - Upholstered Household Furniture |
Sales | $10,000,000-$50,000,000 |
# of Employees | 122 |
Plant Area (Sq.Ft.) | 258,933 |
Annual Production | 140,000 Pieces |
Production Hrs. Annual | 7,500 |
Location (State) | NC |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $319,018 | 5,454,090 | kWh | $0.06 |
Electricity Demand | $48,071 | 10,752 | kW-months/year | $4.47 |
Wood | $21,080 | 7,492 | MMBtu | $2.81 |
TOTAL ENERGY COSTS | $388,169 | |||
RECOMMENDED SAVINGS* | $82,847 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $68,617 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Personnel Changes | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4226 USE / PURCHASE OPTIMUM SIZED COMPRESSOR |
Savings: $13,092 Cost: $8,000 |
$13,092 | 223,800 | - | - | - | - | - | - |
$13,092 223,800 kWh |
- - kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $2,608 Cost: $100 |
$2,314 | 39,555 | $294 | 66 | - | - | - | - |
$2,314 39,555 kWh |
$294 66 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $1,361 Cost: $200 |
$1,694 | 28,954 | $207 | 46 | $(-300) | - | $(-240) | - |
$1,694 28,954 kWh |
$207 46 kW-months/year |
$(-300) - $ |
$(-240) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE |
Savings: $552 Cost: $1,500 |
$474 | 8,100 | $78 | 17 | - | - | - | - |
$474 8,100 kWh |
$78 17 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $48,868 Cost: $143,752 |
$42,208 | 721,503 | $6,660 | 1,490 | - | - | - | - |
$42,208 721,503 kWh |
$6,660 1,490 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $9,769 Cost: $32,929 |
$7,148 | 122,180 | $2,621 | 586 | - | - | - | - |
$7,148 122,180 kWh |
$2,621 586 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $1,138 Cost: $1,215 |
$1,138 | 19,456 | - | - | - | - | - | - |
$1,138 19,456 kWh |
- - kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $863 Cost: $300 |
$375 | 6,412 | $39 | 9 | - | - | $449 | - |
$375 6,412 kWh |
$39 9 kW-months/year |
- - $ |
$449 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE |
Savings: $2,806 Cost: $4,000 |
$2,806 | 47,962 | - | - | - | - | - | - |
$2,806 47,962 kWh |
- - kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.4151 DEVELOP A REPAIR/REPLACE POLICY |
Savings: $977 Cost: $4,256 |
$707 | 12,089 | $270 | 60 | - | - | - | - |
$707 12,089 kWh |
$270 60 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $813 Cost: $281 |
$589 | 10,062 | $224 | 50 | - | - | - | - |
$589 10,062 kWh |
$224 50 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $82,847 Cost: $196,533 |
$72,545 | 1,240,073 | $10,393 | 2,324 | $(-300) | - | $209 | - | $72,545 1,240,073 kWh |
$10,393 2,324 kW-months/year |
$(-300) - $ |
$209 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $68,617 Cost: $187,318 |
$58,315 | 996,817 | $10,393 | 2,324 | $(-300) | - | $209 | - | $58,315 996,817 kWh |
$10,393 2,324 kW-months/year |
$(-300) - $ |
$209 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Personnel Changes | Ancillary Material Cost |