Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
18
matching recommendationsSIC | 2522 | Office Furniture, Except Wood |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MS0228 # 06 Y:2003 | 06 | 2003 | INSULATE BARE EQUIPMENT | $90 | $157 | Not Implemented |
MS0228 # 05 Y:2003 | 05 | 2003 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $323 | $0 | Implemented |
MS0228 # 04 Y:2003 | 04 | 2003 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,237 | $1,210 | Not Implemented |
MS0228 # 03 Y:2003 | 03 | 2003 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,499 | $2,540 | Implemented |
MS0228 # 02 Y:2003 | 02 | 2003 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,344 | $276 | Implemented |
MS0228 # 01 Y:2003 | 01 | 2003 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $4,861 | $6,210 | Not Implemented |
MS0104 # 04 Y:1998 | 04 | 1998 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $397 | $0 | Implemented |
MS0104 # 06 Y:1998 | 06 | 1998 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $13,962 | $27,800 | Implemented |
MS0104 # 05 Y:1998 | 05 | 1998 | INCREASE AMOUNT OF WASTE RECOVERED FOR RESALE | $3,224 | $1,080 | Not Implemented |
MS0104 # 03 Y:1998 | 03 | 1998 | RECOVER WASTE HEAT FROM EQUIPMENT | $5,872 | $12,115 | Implemented |
MS0104 # 02 Y:1998 | 02 | 1998 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $12,499 | $3,080 | Not Implemented |
MS0104 # 01 Y:1998 | 01 | 1998 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,476 | $54 | Implemented |
MS0020 # 01 Y:1995 | 01 | 1995 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $8,151 | $1,500 | Not Implemented |
MS0020 # 06 Y:1995 | 06 | 1995 | INSTALL OCCUPANCY SENSORS | $220 | $150 | Not Implemented |
MS0020 # 05 Y:1995 | 05 | 1995 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $687 | $2,000 | Not Implemented |
MS0020 # 04 Y:1995 | 04 | 1995 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $1,412 | $0 | Implemented |
MS0020 # 03 Y:1995 | 03 | 1995 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $4,180 | $8,000 | Implemented |
MS0020 # 02 Y:1995 | 02 | 1995 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $6,400 | $18,000 | Not Implemented |