IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

20

matching recommendations
Reset
SIC 2541 Wood Partitions And Fixtures
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
TN0658 # 01 Y:1999 01 1999 BURN WOOD BY-PRODUCTS FOR HEAT $194,600 $52,000 Not Implemented
TN0658 # 10 Y:1999 10 1999 USE SYNTHETIC LUBRICANT $650 $0 Not Implemented
TN0658 # 09 Y:1999 09 1999 RECOVER WASTE HEAT FROM EQUIPMENT $700 $810 Not Implemented
TN0658 # 08 Y:1999 08 1999 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,010 $4,000 Implemented
TN0658 # 07 Y:1999 07 1999 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $1,360 $1,330 Not Implemented
TN0658 # 06 Y:1999 06 1999 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED $2,780 $2,630 Implemented
TN0658 # 05 Y:1999 05 1999 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS $9,160 $1,400 Not Implemented
TN0658 # 04 Y:1999 04 1999 TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY $25,000 $5,500 Implemented
TN0658 # 03 Y:1999 03 1999 CONTRACT A WOOD PALLET RECYCLING COMPANY $112,500 $32,000 Not Implemented
TN0658 # 02 Y:1999 02 1999 RECOVER AND REUSE WASTE MATERIAL $120,000 $2,400 Not Implemented
TN0553 # 04 Y:1995 04 1995 USE DEMAND CONTROLLER OR LOAD SHEDDER $14,284 $20,800 Not Implemented
TN0553 # 03 Y:1995 03 1995 INSTALL SPECTRAL REFLECTORS / DELAMP $853 $0 Implemented
TN0553 # 02 Y:1995 02 1995 USE OPTIMUM SIZE AND CAPACITY EQUIPMENT $3,313 $1,320 Implemented
TN0553 # 01 Y:1995 01 1995 SHUT OFF PILOTS IN STANDBY EQUIPMENT $810 $0 Implemented
TN0465 # 01 Y:1992 01 1992 KEEP LAMPS AND REFLECTORS CLEAN $2,859 $8,652 Not Implemented
TN0465 # 06 Y:1992 06 1992 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $57 $114 Not Implemented
TN0465 # 05 Y:1992 05 1992 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $140 $0 Not Implemented
TN0465 # 04 Y:1992 04 1992 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME $219 $350 Not Implemented
TN0465 # 03 Y:1992 03 1992 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $259 $85 Not Implemented
TN0465 # 02 Y:1992 02 1992 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA $817 $0 Not Implemented