Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
39
matching recommendationsSIC | 2541 | Wood Partitions And Fixtures |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
ND0259 # 05 Y:1996 | 05 | 1996 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $51 | $120 | Not Implemented |
ND0266 # 06 Y:1996 | 06 | 1996 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,688 | $1,200 | Implemented |
ND0266 # 05 Y:1996 | 05 | 1996 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $339 | $610 | Not Implemented |
ND0266 # 04 Y:1996 | 04 | 1996 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $948 | $2,000 | Implemented |
ND0266 # 03 Y:1996 | 03 | 1996 | TURN OFF EQUIPMENT WHEN NOT IN USE | $122 | $87 | Implemented |
ND0266 # 02 Y:1996 | 02 | 1996 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $182 | $440 | Not Implemented |
ND0266 # 01 Y:1996 | 01 | 1996 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,095 | $1,745 | Implemented |
ND0259 # 13 Y:1996 | 13 | 1996 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $400 | $225 | Not Implemented |
ND0259 # 12 Y:1996 | 12 | 1996 | CONVERT TO HIGH VOLUME LOW PRESSURE (HVLP) PAINT GUNS | $2,345 | $800 | Not Implemented |
ND0259 # 11 Y:1996 | 11 | 1996 | ELIMINATE OLD STOCK AND MODIFY INVENTORY CONTROL | $53,610 | $15,230 | Implemented |
ND0259 # 10 Y:1996 | 10 | 1996 | COMBINE UTILITY METERS | $342 | $1,300 | Not Implemented |
ND0259 # 09 Y:1996 | 09 | 1996 | TURN OFF EQUIPMENT WHEN NOT IN USE | $19 | $37 | Implemented |
ND0259 # 08 Y:1996 | 08 | 1996 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $64 | $73 | Implemented |
ND0259 # 07 Y:1996 | 07 | 1996 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $254 | $150 | Implemented |
ND0259 # 06 Y:1996 | 06 | 1996 | PAY UTILITY BILLS ON TIME | $72 | $0 | Implemented |
ND0259 # 04 Y:1996 | 04 | 1996 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $215 | $46 | Implemented |
ND0259 # 03 Y:1996 | 03 | 1996 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $177 | $300 | Not Implemented |
ND0259 # 02 Y:1996 | 02 | 1996 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $704 | $310 | Not Implemented |
ND0259 # 01 Y:1996 | 01 | 1996 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $331 | $897 | Implemented |
ND0266 # 07 Y:1996 | 07 | 1996 | CLOSE HOLES AND OPENINGS IN BUILDING SUCH AS BROKEN WINDOWS | $186 | $350 | Implemented |
ND0266 # 08 Y:1996 | 08 | 1996 | PAY UTILITY BILLS ON TIME | $1,408 | $0 | Implemented |
ND0266 # 09 Y:1996 | 09 | 1996 | OPTIMIZE PRODUCTION LOT SIZES AND INVENTORIES | $53,783 | $23,845 | Implemented |
ND0266 # 10 Y:1996 | 10 | 1996 | COMBINE UTILITY METERS | $9,321 | $4,500 | Not Implemented |
ND0266 # 11 Y:1996 | 11 | 1996 | CONVERT TO ELECTROSTATIC POWDER COATING | $66,480 | $82,000 | Not Implemented |
SF0091 # 05 Y:1996 | 05 | 1996 | INCREASE AMOUNT OF WASTE RECOVERED FOR RESALE | $1,017 | $0 | Not Implemented |