Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
471
matching recommendationsSIC | 26 | Paper And Allied Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AM0197 # 06 Y:1994 | 06 | 1994 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $473 | $919 | Not Implemented |
AM0197 # 07 Y:1994 | 07 | 1994 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $220 | $0 | Implemented |
AM0187 # 01 Y:1993 | 01 | 1993 | TURN OFF EQUIPMENT WHEN NOT IN USE | $16,530 | $465 | Not Implemented |
AM0187 # 02 Y:1993 | 02 | 1993 | USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY | $6,720 | $0 | Implemented |
AM0187 # 03 Y:1993 | 03 | 1993 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $3,800 | $370 | Implemented |
AM0187 # 04 Y:1993 | 04 | 1993 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $2,150 | $1,000 | Implemented |
AM0187 # 05 Y:1993 | 05 | 1993 | MAINTAIN AIR FILTERS BY CLEANING OR REPLACEMENT | $2,130 | $0 | Not Implemented |
AM0187 # 06 Y:1993 | 06 | 1993 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,740 | $1,882 | Not Implemented |
AM0187 # 07 Y:1993 | 07 | 1993 | USE SYNTHETIC LUBRICANT | $190 | $0 | Implemented |
AM0180 # 01 Y:1993 | 01 | 1993 | OPERATE DISTILLATION COLUMNS EFFICIENTLY | $3,360 | $13,900 | Not Implemented |
AM0180 # 02 Y:1993 | 02 | 1993 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $2,570 | $1,515 | Not Implemented |
AM0180 # 03 Y:1993 | 03 | 1993 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $1,650 | $0 | Not Implemented |
AM0180 # 04 Y:1993 | 04 | 1993 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $755 | $400 | Implemented |
AM0180 # 05 Y:1993 | 05 | 1993 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $640 | $1,115 | Implemented |
AM0165 # 01 Y:1992 | 01 | 1992 | USE DRYING OVEN (BATCH TYPE) ON ALTERNATE DAYS OR OTHER OPTIMUM SCHEDULE TO RUN EQUIPMENT WITH FULL LOADS | $23,570 | $1,350 | Implemented |
AM0165 # 02 Y:1992 | 02 | 1992 | LOWER CEILING TO REDUCE CONDITIONED SPACE | $6,300 | $3,630 | Implemented |
AM0165 # 03 Y:1992 | 03 | 1992 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $3,915 | $3,450 | Not Implemented |
AM0165 # 04 Y:1992 | 04 | 1992 | REDUCE FLUID FLOW RATES | $2,710 | $0 | Not Implemented |
AM0165 # 05 Y:1992 | 05 | 1992 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,750 | $0 | Not Implemented |
AM0165 # 06 Y:1992 | 06 | 1992 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,330 | $2,520 | Implemented |
AM0165 # 07 Y:1992 | 07 | 1992 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $920 | $920 | Not Implemented |
AM0165 # 08 Y:1992 | 08 | 1992 | INSTALL SET-BACK TIMERS | $150 | $190 | Implemented |
AM0061 # 01 Y:1989 | 01 | 1989 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $7,000 | $270 | Implemented |
AM0061 # 02 Y:1989 | 02 | 1989 | OPTIMIZE PLANT POWER FACTOR | $18,950 | $29,790 | Implemented |
AM0061 # 03 Y:1989 | 03 | 1989 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $14,660 | $19,050 | Not Implemented |