Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
476
matching recommendationsSIC | 26 | Paper And Allied Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
NT0029 # 04 Y:2024 | 04 | 2024 | APPLY FOR INVESTMENT INCENTIVES | $204,971 | $10,000 | n/a |
NT0029 # 05 Y:2024 | 05 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $8,550 | $21,900 | n/a |
NT0029 # 02 Y:2024 | 02 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $8,227 | $1,819 | n/a |
NT0029 # 03 Y:2024 | 03 | 2024 | OPTIMIZE PLANT POWER FACTOR | $34,386 | $117,351 | n/a |
NT0029 # 01 Y:2024 | 01 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,179 | $5,609 | n/a |
NT0023 # 02 Y:2024 | 02 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $21,899 | $15,284 | n/a |
NT0023 # 05 Y:2024 | 05 | 2024 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $2,130 | $17,836 | n/a |
NT0023 # 06 Y:2024 | 06 | 2024 | CHANGE OPERATING CONDITIONS | $150,000 | $616,838 | n/a |
NT0023 # 04 Y:2024 | 04 | 2024 | APPLY FOR INVESTMENT INCENTIVES | $7,720 | $0 | n/a |
NT0023 # 03 Y:2024 | 03 | 2024 | OPTIMIZE PLANT POWER FACTOR | $36,182 | $16,564 | n/a |
NT0023 # 01 Y:2024 | 01 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,070 | $5,609 | n/a |
NT0014 # 03 Y:2023 | 03 | 2023 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $955 | $0 | Implemented |
NT0014 # 05 Y:2023 | 05 | 2023 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $5,512 | $0 | Implemented |
NT0014 # 01 Y:2023 | 01 | 2023 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $9,483 | $1,258 | Implemented |
NT0014 # 02 Y:2023 | 02 | 2023 | CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD | $6,006 | $6,160 | Implemented |
NT0014 # 04 Y:2023 | 04 | 2023 | OPTIMIZE PLANT POWER FACTOR | $2,486 | $1,441 | Implemented |
AM0787 # 08 Y:2019 | 08 | 2019 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $399 | $280 | Not Implemented |
AM0787 # 07 Y:2019 | 07 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,577 | $2,640 | Implemented |
AM0787 # 06 Y:2019 | 06 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,322 | $825 | Implemented |
AM0787 # 01 Y:2019 | 01 | 2019 | USE STEAM PRESSURE REDUCTION TO GENERATE POWER | $290,927 | $1,011,274 | Not Implemented |
AM0787 # 02 Y:2019 | 02 | 2019 | USE COMBINED CYCLE GAS TURBINE GENERATOR SETS WITH WASTE HEAT BOILERS CONNECTED TO TURBINE EXHAUST | $312,044 | $849,614 | Not Implemented |
AM0787 # 03 Y:2019 | 03 | 2019 | REPAIR OR REPLACE STEAM TRAPS | $56,595 | $10,440 | Implemented |
AM0787 # 04 Y:2019 | 04 | 2019 | USE SYNTHETIC LUBRICANT | $13,271 | $14,560 | Implemented |
AM0787 # 05 Y:2019 | 05 | 2019 | OPTIMIZE PLANT POWER FACTOR | $70,814 | $178,864 | Implemented |
AM0784 # 03 Y:2019 | 03 | 2019 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $5,980 | $1,400 | Implemented |