Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
20
matching recommendationsSIC | 2621 | Paper Mills |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
NC0270 # 06 Y:2003 | 06 | 2003 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,246 | $2,400 | Implemented |
NC0270 # 05 Y:2003 | 05 | 2003 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $4,551 | $0 | Implemented |
NC0270 # 04 Y:2003 | 04 | 2003 | ADJUST BURNERS FOR EFFICIENT OPERATION | $16,620 | $1,000 | Implemented |
NC0270 # 03 Y:2003 | 03 | 2003 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $15,758 | $45,000 | Not Implemented |
NC0270 # 02 Y:2003 | 02 | 2003 | TREAT AND REUSE RINSE WATERS | $71,629 | $300,000 | Not Implemented |
NC0270 # 01 Y:2003 | 01 | 2003 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $149,890 | $50,000 | Implemented |
NC0174 # 03 Y:1999 | 03 | 1999 | ADJUST BURNERS FOR EFFICIENT OPERATION | $858 | $700 | Implemented |
NC0174 # 06 Y:1999 | 06 | 1999 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $3,443 | $3,520 | Not Implemented |
NC0174 # 05 Y:1999 | 05 | 1999 | RECOVER WASTE HEAT FROM EQUIPMENT | $22,630 | $13,000 | Implemented |
NC0174 # 04 Y:1999 | 04 | 1999 | INSULATE BARE EQUIPMENT | $1,535 | $1,006 | Not Implemented |
NC0174 # 02 Y:1999 | 02 | 1999 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $504 | $150 | Implemented |
NC0174 # 01 Y:1999 | 01 | 1999 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $9,777 | $2,000 | Not Implemented |
AT0081 # 01 Y:1987 | 01 | 1987 | USE COMBINED CYCLE GAS TURBINE GENERATOR SETS WITH WASTE HEAT BOILERS CONNECTED TO TURBINE EXHAUST | $255,410 | $1,000,000 | Not Implemented |
AT0081 # 08 Y:1987 | 08 | 1987 | INSTALL / REPAIR INSULATION ON CONDENSATE LINES | $464 | $240 | Implemented |
AT0081 # 07 Y:1987 | 07 | 1987 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $5,796 | $6,000 | Implemented |
AT0081 # 06 Y:1987 | 06 | 1987 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $9,252 | $6,000 | Implemented |
AT0081 # 05 Y:1987 | 05 | 1987 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $815 | $1,800 | Implemented |
AT0081 # 04 Y:1987 | 04 | 1987 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,062 | $2,365 | Implemented |
AT0081 # 03 Y:1987 | 03 | 1987 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,541 | $0 | Implemented |
AT0081 # 02 Y:1987 | 02 | 1987 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $966 | $1,074 | Implemented |