Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

219

matching recommendations
Reset
SIC 265 Paperboard Containers And Boxes
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
DL0218 # 06 Y:2023 06 2023 INSTALL SET-BACK TIMERS $473 $1,000 Not Implemented
DL0218 # 05 Y:2023 05 2023 RECOVER WASTE HEAT FROM EQUIPMENT $11,159 $10,000 Implemented
DL0218 # 04 Y:2023 04 2023 SHUT OFF COOLING IF COLD OUTSIDE AIR WILL COOL PROCESS $10,992 $10,000 Not Implemented
DL0218 # 03 Y:2023 03 2023 RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR $3,402 $750 Implemented
DL0218 # 02 Y:2023 02 2023 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED $90,882 $0 Implemented
DL0218 # 01 Y:2023 01 2023 REDUCE VENTILATION AIR $11,809 $0 Implemented
DL0150 # 02 Y:2015 02 2015 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,920 $500 Not Implemented
DL0150 # 07 Y:2015 07 2015 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $3,720 $18,100 Not Implemented
DL0150 # 06 Y:2015 06 2015 LOWER CEILING TO REDUCE CONDITIONED SPACE $13,240 $62,400 Not Implemented
DL0150 # 05 Y:2015 05 2015 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $6,075 $19,740 Not Implemented
DL0150 # 04 Y:2015 04 2015 INSTALL REPLACEMENT DOORS $2,450 $7,800 Not Implemented
DL0150 # 03 Y:2015 03 2015 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS $760 $560 Not Implemented
DL0150 # 01 Y:2015 01 2015 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED $780 $0 Not Implemented
DL0150 # 08 Y:2015 08 2015 CONVERT COMBUSTION EQUIPMENT TO BURN NATURAL GAS $7,020 $58,500 Not Implemented
LE0397 # 04 Y:2015 04 2015 USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING $2,238 $5,500 Not Implemented
LE0397 # 01 Y:2015 01 2015 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $7,085 $4,300 Not Implemented
LE0397 # 06 Y:2015 06 2015 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $116 $1,914 Implemented
LE0397 # 05 Y:2015 05 2015 USE / PURCHASE OPTIMUM SIZED COMPRESSOR $4,917 $14,900 Not Implemented
LE0397 # 03 Y:2015 03 2015 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,396 $1,000 Implemented
LE0397 # 02 Y:2015 02 2015 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $14,221 $10,086 Implemented
LE0336 # 07 Y:2012 07 2012 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $2,762 $25 Implemented
LE0336 # 04 Y:2012 04 2012 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $7,734 $8,000 Implemented
LE0336 # 06 Y:2012 06 2012 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $2,840 $3,000 Implemented
LE0336 # 09 Y:2012 09 2012 INSTALL SOFT-START TO ELIMINATE NUISANCE TRIPS $2,523 $2,500 Not Implemented
LE0336 # 10 Y:2012 10 2012 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $576 $840 Not Implemented