Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
3,551
matching recommendationsSIC | 265 | Paperboard Containers And Boxes |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
WV0171 # 10 Y:1999 | 10 | 1999 | CONTRACT A WOOD PALLET RECYCLING COMPANY | $1,200 | $42 | Implemented |
WV0171 # 11 Y:1999 | 11 | 1999 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $54,912 | $0 | Not Implemented |
WV0171 # 12 Y:1999 | 12 | 1999 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $3,955 | $1,000 | Not Implemented |
WV0171 # 13 Y:1999 | 13 | 1999 | APPLY FOR INVESTMENT INCENTIVES | $34,699 | $0 | Implemented |
UF0226 # 01 Y:1999 | 01 | 1999 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,552 | $0 | Not Implemented |
UF0226 # 02 Y:1999 | 02 | 1999 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,196 | $0 | Not Implemented |
UF0226 # 03 Y:1999 | 03 | 1999 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $10,378 | $50 | Not Implemented |
UF0226 # 04 Y:1999 | 04 | 1999 | INSTALL OCCUPANCY SENSORS | $1,110 | $955 | Not Implemented |
UF0226 # 05 Y:1999 | 05 | 1999 | INITIATE A TOTAL QUALITY MANAGEMENT PROGRAM | $78,207 | $22,390 | Not Implemented |
UF0226 # 06 Y:1999 | 06 | 1999 | USE WASTE HEAT WITH A CLOSED-CYCLE GAS TURBINE-GENERATOR SET TO COGENERATE ELECTRICITY AND HEAT | $200,838 | $1,090,000 | Not Implemented |
UF0226 # 07 Y:1999 | 07 | 1999 | PAY BILLS ON TIME TO AVOID LATE FEES | $1,863 | $0 | Not Implemented |
OR0345 # 06 Y:1999 | 06 | 1999 | SEPARATE AND RECYCLE SCRAP METAL TO FOUNDRY OR FOR SALE | $1,560 | $9,635 | Not Implemented |
OR0345 # 01 Y:1999 | 01 | 1999 | INSTALL EQUIPMENT TO MOVE PRODUCT | $22,460 | $13,140 | Not Implemented |
OR0345 # 02 Y:1999 | 02 | 1999 | CONVERT COMBUSTION EQUIPMENT TO BURN NATURAL GAS | $6,490 | $44,000 | Not Implemented |
OR0345 # 03 Y:1999 | 03 | 1999 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $4,284 | $65 | Not Implemented |
OR0345 # 04 Y:1999 | 04 | 1999 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $446 | $1,000 | Implemented |
OR0345 # 05 Y:1999 | 05 | 1999 | SELL COMBUSTIBLE WASTE | $2,590 | $0 | Not Implemented |
CO0437 # 01 Y:1999 | 01 | 1999 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $10,300 | $7,500 | Not Implemented |
CO0437 # 02 Y:1999 | 02 | 1999 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,280 | $1,000 | Not Implemented |
CO0437 # 03 Y:1999 | 03 | 1999 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $1,190 | $2,720 | Not Implemented |
CO0437 # 04 Y:1999 | 04 | 1999 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $90 | $958 | Not Implemented |
CO0437 # 05 Y:1999 | 05 | 1999 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $790 | $1,650 | Not Implemented |
CO0437 # 06 Y:1999 | 06 | 1999 | MODIFY PROCESS TO REDUCE MATERIAL USE/COST | $104,000 | $1,500 | Not Implemented |
CO0437 # 07 Y:1999 | 07 | 1999 | $59,470 | $20,000 | Not Implemented | |
AR0161 # 01 Y:1999 | 01 | 1999 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $8,867 | $161 | Not Implemented |