Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
2,547
matching recommendationsSIC | 2653 | Corrugated And Solid Fiber Boxes |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
KU0134 # 16 Y:1984 | 16 | 1984 | RECOVER WASTE HEAT FROM EQUIPMENT | $2,474 | $350 | Not Implemented |
KU0134 # 17 Y:1984 | 17 | 1984 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $885 | $680 | Not Implemented |
KU0134 # 18 Y:1984 | 18 | 1984 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $3,284 | $6,000 | Not Implemented |
KU0134 # 19 Y:1984 | 19 | 1984 | INSULATE BARE EQUIPMENT | $2,213 | $550 | Not Implemented |
KU0134 # 20 Y:1984 | 20 | 1984 | INSULATE BARE EQUIPMENT | $1,264 | $241 | Not Implemented |
KU0134 # 21 Y:1984 | 21 | 1984 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $569 | $0 | Not Implemented |
KU0134 # 22 Y:1984 | 22 | 1984 | INSULATE BARE EQUIPMENT | $508 | $60 | Not Implemented |
KU0134 # 23 Y:1984 | 23 | 1984 | REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED | $395 | $250 | Implemented |
KU0134 # 24 Y:1984 | 24 | 1984 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $340 | $41 | Not Implemented |
KU0138 # 01 Y:1984 | 01 | 1984 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,748 | $0 | Implemented |
KU0138 # 02 Y:1984 | 02 | 1984 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $177 | $250 | Implemented |
KU0138 # 03 Y:1984 | 03 | 1984 | INSTALL SET-BACK TIMERS | $1,100 | $0 | Implemented |
KU0138 # 04 Y:1984 | 04 | 1984 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $1,807 | $200 | Implemented |
KU0138 # 05 Y:1984 | 05 | 1984 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $1,535 | $2,500 | Not Implemented |
KU0138 # 06 Y:1984 | 06 | 1984 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $314 | $0 | Not Implemented |
KU0138 # 07 Y:1984 | 07 | 1984 | IMPROVE LUBRICATION PRACTICES | $4,026 | $1,000 | Not Implemented |
KU0138 # 08 Y:1984 | 08 | 1984 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $1,100 | $450 | Not Implemented |
KU0138 # 10 Y:1984 | 10 | 1984 | INSTALL AUTOMATIC STACK DAMPER | $2,518 | $1,600 | Not Implemented |
KU0138 # 11 Y:1984 | 11 | 1984 | INSTALL TIMERS AND/OR THERMOSTATS | $661 | $0 | Implemented |
KU0138 # 12 Y:1984 | 12 | 1984 | ESTABLISH EQUIPMENT MAINTENANCE SCHEDULE | $884 | $120 | Implemented |
KU0138 # 13 Y:1984 | 13 | 1984 | REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED | $112 | $0 | Not Implemented |
UD0130 # 01 Y:1984 | 01 | 1984 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $47,885 | $110,000 | Not Implemented |
UD0130 # 02 Y:1984 | 02 | 1984 | REDUCE GLAZED AREAS IN BUILDINGS | $7,927 | $5,145 | Not Implemented |
UD0130 # 03 Y:1984 | 03 | 1984 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $466 | $578 | Not Implemented |
UD0130 # 04 Y:1984 | 04 | 1984 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $26,850 | $30,000 | Not Implemented |