Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
21
matching recommendationsSIC | 2655 | Fiber Cans, Drums & Similar Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
KU0157 # 09 Y:1985 | 09 | 1985 | INSTALL AUTOMATIC STACK DAMPER | $745 | $1,100 | Implemented |
KU0157 # 08 Y:1985 | 08 | 1985 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $357 | $0 | Implemented |
KU0157 # 07 Y:1985 | 07 | 1985 | RECOVER WASTE HEAT FROM EQUIPMENT | $899 | $1,480 | Implemented |
KU0157 # 06 Y:1985 | 06 | 1985 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,893 | $1,500 | Implemented |
KU0157 # 05 Y:1985 | 05 | 1985 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $759 | $1,016 | Implemented |
KU0157 # 04 Y:1985 | 04 | 1985 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,889 | $1,550 | Implemented |
KU0157 # 03 Y:1985 | 03 | 1985 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,260 | $4,000 | Implemented |
KU0157 # 02 Y:1985 | 02 | 1985 | IMPROVE LUBRICATION PRACTICES | $1,569 | $290 | Implemented |
KU0157 # 01 Y:1985 | 01 | 1985 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $19,738 | $2,752 | Not Implemented |
KU0064 # 11 Y:1982 | 11 | 1982 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $2,002 | $882 | Not Implemented |
KU0064 # 12 Y:1982 | 12 | 1982 | REPLACE BOILER | $1,205 | $3,200 | Not Implemented |
KU0064 # 01 Y:1982 | 01 | 1982 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $11,639 | $8,528 | Not Implemented |
KU0064 # 10 Y:1982 | 10 | 1982 | INSTALL AUTOMATIC STACK DAMPER | $2,357 | $1,365 | Not Implemented |
KU0064 # 09 Y:1982 | 09 | 1982 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $2,891 | $150 | Not Implemented |
KU0064 # 08 Y:1982 | 08 | 1982 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $4,469 | $643 | Implemented |
KU0064 # 07 Y:1982 | 07 | 1982 | RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR | $5,136 | $8,125 | Not Implemented |
KU0064 # 06 Y:1982 | 06 | 1982 | USE HOT PROCESS FLUIDS TO PREHEAT INCOMING PROCESS FLUIDS | $8,191 | $19,400 | Not Implemented |
KU0064 # 05 Y:1982 | 05 | 1982 | INSTALL TIMERS AND/OR THERMOSTATS | $6,755 | $6,659 | Not Implemented |
KU0064 # 04 Y:1982 | 04 | 1982 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $8,128 | $7,500 | Implemented |
KU0064 # 03 Y:1982 | 03 | 1982 | OPTIMIZE PLANT POWER FACTOR | $15,210 | $7,760 | Not Implemented |
KU0064 # 02 Y:1982 | 02 | 1982 | USE OPTIMUM SIZE AND CAPACITY EQUIPMENT | $20,021 | $5,480 | Not Implemented |