Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,398
matching recommendationsSIC | 267 | Misc. Converted Paper Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
BD0459 # 05 Y:2015 | 05 | 2015 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $2,648 | $2,700 | Implemented |
BD0459 # 06 Y:2015 | 06 | 2015 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,004 | $300 | Implemented |
BD0459 # 07 Y:2015 | 07 | 2015 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $7,002 | $30,399 | Implemented |
BD0459 # 08 Y:2015 | 08 | 2015 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $377 | $800 | Implemented |
BD0459 # 09 Y:2015 | 09 | 2015 | LOWER COMPRESSOR PRESSURE THROUGH A/C SYSTEM MODIFICATION | $142 | $20 | Implemented |
BD0459 # 10 Y:2015 | 10 | 2015 | USE RADIANT HEATER FOR SPOT HEATING | $1,263 | $3,500 | Implemented |
BD0459 # 11 Y:2015 | 11 | 2015 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $3,826 | $18 | Implemented |
BD0449 # 01 Y:2014 | 01 | 2014 | USE OUTSIDE COLD WATER SOURCE AS A SUPPLY OF COOLING WATER | $64,237 | $1,500,000 | Implemented |
BD0449 # 03 Y:2014 | 03 | 2014 | USE PHOTOCELL CONTROLS | $12,784 | $7,575 | Implemented |
BD0449 # 06 Y:2014 | 06 | 2014 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,491 | $20 | Implemented |
BD0449 # 08 Y:2014 | 08 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,827 | $2,800 | Implemented |
LE0383 # 01 Y:2014 | 01 | 2014 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,489 | $40 | Implemented |
LE0383 # 02 Y:2014 | 02 | 2014 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,539 | $300 | Implemented |
NC0519 # 01 Y:2014 | 01 | 2014 | USE OPTIMUM SIZE AND CAPACITY EQUIPMENT | $207,427 | $102,000 | Implemented |
NC0519 # 03 Y:2014 | 03 | 2014 | USE HOT PROCESS FLUIDS TO PREHEAT INCOMING PROCESS FLUIDS | $104,811 | $52,500 | Implemented |
NC0519 # 04 Y:2014 | 04 | 2014 | REPAIR AND ELIMINATE STEAM LEAKS | $21,819 | $2,200 | Implemented |
NC0519 # 05 Y:2014 | 05 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $67,692 | $258,028 | Implemented |
NC0519 # 06 Y:2014 | 06 | 2014 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,850 | $500 | Implemented |
MZ0147 # 01 Y:2014 | 01 | 2014 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $871 | $360 | Implemented |
MZ0147 # 02 Y:2014 | 02 | 2014 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $63 | $235 | Implemented |
MZ0147 # 03 Y:2014 | 03 | 2014 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $63 | $235 | Implemented |
MZ0147 # 04 Y:2014 | 04 | 2014 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $423 | $470 | Implemented |
MZ0147 # 05 Y:2014 | 05 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $10,562 | $42,645 | Implemented |
MZ0147 # 06 Y:2014 | 06 | 2014 | USE SEPARATE SWITCHES ON PERIMETER LIGHTING WHICH MAY BE TURNED OFF WHEN NATURAL LIGHT IS AVAILABLE | $1,184 | $600 | Implemented |
MZ0147 # 09 Y:2014 | 09 | 2014 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $4,212 | $420 | Implemented |