Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | North Carolina State |
---|---|
Assessment Year | 2015 |
Principal Product | Cardboard retail displays |
NAICS | 322230 - Stationery Product Manufacturing |
SIC | 2675 - Die-cut Paper And Board |
Sales | $10,000,000-$50,000,000 |
# of Employees | 65 |
Plant Area (Sq.Ft.) | 100,000 |
Annual Production | 77,000 Thousand Feet |
Production Hrs. Annual | 2,250 |
Location (State) | NC |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $69,990 | 1,078,656 | kWh | $0.06 |
Electricity Demand | $22,755 | 6,897 | kW-months/year | $3.30 |
Natural Gas | $6,333 | 893 | MMBtu | $7.09 |
TOTAL ENERGY COSTS | $99,078 | |||
RECOMMENDED SAVINGS* | $34,843 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $700 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Ancillary Material Cost | Increase in Production | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Ancillary Material Cost | Increase in Production | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | $ | % | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 4.625 DEVELOP STANDARD OPERATING PROCEDURES |
Savings: $27,300 Cost: $10,000 |
- | - | - | - | - | - | - | - | - | - | $27,300 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
- - $ |
$27,300 - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS |
Savings: $2,334 Cost: $1,131 |
$1,692 | 26,064 | $458 | 139 | - | - | - | - | $184 | - | - | - |
$1,692 26,064 kWh |
$458 139 kW-months/year |
- - MMBtu |
- - $ |
$184 - $ |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $596 Cost: $160 |
$277 | 4,275 | $20 | 6 | - | - | - | - | $299 | - | - | - |
$277 4,275 kWh |
$20 6 kW-months/year |
- - MMBtu |
- - $ |
$299 - $ |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $299 Cost: $405 |
$213 | 3,281 | $58 | 18 | - | - | - | - | $28 | - | - | - |
$213 3,281 kWh |
$58 18 kW-months/year |
- - MMBtu |
- - $ |
$28 - $ |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $536 Cost: $918 |
$536 | 8,267 | - | - | - | - | - | - | - | - | - | - |
$536 8,267 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
- - $ |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7313 RECYCLE AIR FOR HEATING, VENTILATION AND AIR CONDITIONING |
Savings: $1,054 Cost: $5,000 |
- | - | - | - | $1,054 | 149 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$1,054 149 MMBtu |
- - $ |
- - $ |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $634 Cost: $3,000 |
$499 | 7,695 | $135 | 41 | - | - | - | - | - | - | - | - |
$499 7,695 kWh |
$135 41 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $627 Cost: $470 |
- | - | - | - | $627 | 88 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$627 88 MMBtu |
- - $ |
- - $ |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $104 Cost: $100 |
$176 | 2,719 | $48 | 14 | - | - | $(-100) | - | $(-20) | - | - | - |
$176 2,719 kWh |
$48 14 kW-months/year |
- - MMBtu |
$(-100) - $ |
$(-20) - $ |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE |
Savings: $116 Cost: $240 |
$116 | 1,784 | - | - | - | - | - | - | - | - | - | - |
$116 1,784 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
- - $ |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 2.4151 DEVELOP A REPAIR/REPLACE POLICY |
Savings: $935 Cost: $4,256 |
$736 | 11,333 | $199 | 60 | - | - | - | - | - | - | - | - |
$736 11,333 kWh |
$199 60 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
12: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $308 Cost: $600 |
$308 | 4,741 | - | - | - | - | - | - | - | - | - | - |
$308 4,741 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
- - $ |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $34,843 Cost: $26,280 |
$4,553 | 70,159 | $918 | 278 | $1,681 | 237 | $(-100) | - | $491 | - | $27,300 | - | $4,553 70,159 kWh |
$918 278 kW-months/year |
$1,681 237 MMBtu |
$(-100) - $ |
$491 - $ |
$27,300 - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $700 Cost: $260 |
$453 | 6,994 | $68 | 20 | - | - | $(-100) | - | $279 | - | - | - | $453 6,994 kWh |
$68 20 kW-months/year |
- - MMBtu |
$(-100) - $ |
$279 - $ |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | $ | % | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Ancillary Material Cost | Increase in Production | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Ancillary Material Cost | Increase in Production |