IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

18

matching recommendations
Reset
SIC 2672 Paper Coated And Laminated, Nec
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
BD0376 # 08 Y:2010 08 2010 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $989 $1,727 Implemented
BD0376 # 07 Y:2010 07 2010 USE RADIANT HEATER FOR SPOT HEATING $7,210 $9,000 Not Implemented
BD0376 # 06 Y:2010 06 2010 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $11,590 $5,500 Implemented
BD0376 # 05 Y:2010 05 2010 INSTALL TURBULATORS $20,378 $4,350 Not Implemented
BD0376 # 04 Y:2010 04 2010 RECOVER WASTE HEAT FROM EQUIPMENT $39,238 $34,000 Implemented
BD0376 # 03 Y:2010 03 2010 RECOVER WASTE HEAT FROM EQUIPMENT $62,913 $70,000 Implemented
BD0376 # 02 Y:2010 02 2010 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $67,200 $125 Not Implemented
BD0376 # 01 Y:2010 01 2010 REPLACE OBSOLETE BURNERS WITH MORE EFFICIENT ONES $105,011 $51,500 Implemented
BD0280 # 10 Y:2005 10 2005 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES $708 $750 Not Implemented
BD0280 # 01 Y:2005 01 2005 RECOVER WASTE HEAT FROM EQUIPMENT $34,711 $34,000 Not Implemented
BD0280 # 09 Y:2005 09 2005 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $1,944 $0 Implemented
BD0280 # 08 Y:2005 08 2005 DIRECT WARMEST AIR TO COMBUSTION INTAKE $3,413 $2,000 Implemented
BD0280 # 07 Y:2005 07 2005 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $3,514 $1,400 Implemented
BD0280 # 06 Y:2005 06 2005 RECOVER WASTE HEAT FROM EQUIPMENT $5,694 $9,500 Not Implemented
BD0280 # 05 Y:2005 05 2005 ADJUST BURNERS FOR EFFICIENT OPERATION $10,110 $1,000 Implemented
BD0280 # 04 Y:2005 04 2005 INSTALL OCCUPANCY SENSORS $10,565 $5,850 Implemented
BD0280 # 03 Y:2005 03 2005 ADJUST BURNERS FOR EFFICIENT OPERATION $13,187 $1,000 Not Implemented
BD0280 # 02 Y:2005 02 2005 USE RADIANT HEATER FOR SPOT HEATING $30,129 $31,500 Not Implemented