Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
87
matching recommendationsSIC | 27 | Printing And Publishing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UA0133 # 09 Y:2015 | 09 | 2015 | INSTALL TIMERS AND/OR THERMOSTATS | $2,180 | $0 | Implemented |
UA0133 # 01 Y:2015 | 01 | 2015 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $13,351 | $1,728 | Implemented |
UA0133 # 05 Y:2015 | 05 | 2015 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $8,308 | $10,240 | Implemented |
UA0133 # 03 Y:2015 | 03 | 2015 | INSTALL OCCUPANCY SENSORS | $3,600 | $2,389 | Not Implemented |
UA0133 # 07 Y:2015 | 07 | 2015 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,421 | $50 | Implemented |
UA0133 # 10 Y:2015 | 10 | 2015 | KEEP DOORS AND WINDOWS SHUT WHEN NOT ON USE | $1,848 | $2,636 | Implemented |
UA0133 # 06 Y:2015 | 06 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,161 | $2,500 | Implemented |
UA0133 # 08 Y:2015 | 08 | 2015 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $2,428 | $0 | Not Implemented |
UA0133 # 04 Y:2015 | 04 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,236 | $783 | Implemented |
UA0133 # 02 Y:2015 | 02 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,902 | $13,479 | Implemented |
GT0779 # 07 Y:2004 | 07 | 2004 | INSTALL OCCUPANCY SENSORS | $303 | $1,000 | Implemented |
GT0779 # 01 Y:2004 | 01 | 2004 | REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT | $1,183 | $5,000 | Implemented |
GT0779 # 06 Y:2004 | 06 | 2004 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $1,561 | $320 | Not Implemented |
GT0779 # 02 Y:2004 | 02 | 2004 | REDUCE INFILTRATION TO REFRIGERATED AREAS; ISOLATE HOT EQUIPMENT FROM REFRIGERATED AREAS | $590 | $2,700 | Implemented |
GT0779 # 03 Y:2004 | 03 | 2004 | RECOVER WASTE HEAT FROM EQUIPMENT | $2,642 | $5,350 | Not Implemented |
GT0779 # 04 Y:2004 | 04 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $327 | $300 | Implemented |
GT0779 # 05 Y:2004 | 05 | 2004 | REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT | $2,090 | $4,600 | Not Implemented |
GT0758 # 01 Y:2003 | 01 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $20,720 | $47,268 | Implemented |
GT0758 # 04 Y:2003 | 04 | 2003 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $14,438 | $31,350 | n/a |
GT0758 # 05 Y:2003 | 05 | 2003 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $322 | $0 | Implemented |
GT0758 # 02 Y:2003 | 02 | 2003 | USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE | $9,072 | $12,000 | Implemented |
GT0758 # 03 Y:2003 | 03 | 2003 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $1,895 | $47,736 | n/a |
GT0758 # 07 Y:2003 | 07 | 2003 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $6,773 | $6,150 | Not Implemented |
GT0758 # 08 Y:2003 | 08 | 2003 | METER RECYCLED WATER (TO REDUCE SEWER CHARGES) | $23,420 | $1,850 | Implemented |
GT0758 # 06 Y:2003 | 06 | 2003 | REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT | $28,386 | $12,140 | n/a |